Section 4: Preconstruction Meeting
General
When all sampling and testing has been accomplished, and before
work begins, it is necessary for the Contractor and his representatives
to meet with TxDOT’s representatives. During this meeting a “game
plan” is developed and final details are worked out.
Meeting Objectives
Specifically, the preconstruction meeting should meet the
following objectives:
Meeting All Personnel Involved.
Establish Working Relationship.
Define Responsibilities.
Define Work Schedule.
Review Traffic Control.
Identify Work Days and Holidays.
Miscellaneous.
Attendees
There is no specific rule as to who should attend the preconstruction
meeting. The contractor should be represented by the project supervisor,
foreman, and any other supervisory personnel on the project. It
is highly recommended that the following TxDOT personnel attend
(as a minimum):
- Project Engineer
- Area Engineer (s)
- Maintenance Supervisor (s)
- Director of Maintenance
- District Laboratory Engineer
- Inspectors.
If traffic is expected to be a major factor, sometimes the
Department of Public Safety (DPS) will be represented. Occasionally,
a representative of the local police department will attend, especially
if the project is located in a major metropolitan area. This police
inclusion is recommended.
Any other people who have a direct interest or responsibility
in the project may be invited to attend. This may include the district
public information and safety representatives, Federal Highway Administration
personnel, and occasionally, a representative of the asphalt supplier,
especially if a special binder is specified.