Provisions for Inspection
The contractor and project engineer typically coordinate the
starting date of the project, and set a date and time for the equipment
to be assembled for inspection. It is advisable to set aside a minimum
of half a day for equipment inspection at least one day before seal
coat work begins. Initial equipment inspection should not be done
the first hour or two of the morning the project begins. Even if
all the equipment was functioning correctly on the last project,
equipment problems can occur during the movement of the equipment.
Plenty of time should be allowed to carefully inspect all equipment,
and to allow more time to correct any discrepancies that are found.