8.2 Guidelines for Thin Whitetopping (TWT)
The following guidelines provide the recommendations for TWT design thickness, joint spacing, ACP support layer, and better bond.
- Design Life of 5 to 10 yr. is recommended for TWT.
- Normally used at intersections where rutting and shoving in asphaltic pavement continue to cause problems.
- Designs for < 4 in. TWT were not included because the initial cost difference between 4-in. slabs and those with less than 4 in. is negligible, and thinner slabs require shorter joint spacing, often encroaching on the wheel path.
- Designs for > 7 in. TWT were not included because our standard concrete pavement designs should be used along with load transfer devices.
- Contraction joint spacing is set at 6-ft. intervals to prevent edge loading and reduce the costs for saw cutting. All sawed TWT panels shall be square except as necessary in pavement width transitions.
- Use engineering judgment to allow the contractor to meet plan requirements when using the ride specification at intersections or curb and gutter sections.
- Recommend ≥ 4 in. asphalt concrete pavement (ACP) support layer (including ASB and level-up).
- Uniform support will improve performance.
- Recommend milling the existing ACP to provide a better bond and remove rutting ≥ 1/2 in.
- Opinions differ on the need for fibers to control shrinkage cracking.
- Saw cuts must be made as soon as possible, without delay.
- Saw-cut depths must be adjusted accordingly in thickened end sections.
- At bridge approaches, an approach slab is recommended with an expansion joint as shown in existing standards.
- The department has yet to establish when expansion joints are needed for wide pavements.
- The use of steel fibers is not recommended at locations where de-icing salts may be used.
- Apply governing Special Specification, Thin Whitetopping (Concrete Overlay).
- Use Thin Whitetopping Details, TWT-04 Standard Sheet.
- Use Table 8-8 as a general guide for determining proper TWT thickness. More research will be conducted to improve the design procedure.
Trucks per Day per Lane | Design Life (yr.) | |||||
---|---|---|---|---|---|---|
5 | 6 | 7 | 8 | 9 | 10 | |
≤ 200 | 4 | 4 | 4 | 4 | 4 | 4 |
250 | 4 | 4 | 4 | 4 | 5 | 5 |
300 | 4 | 4 | 4 | 5 | 5 | 5 |
350 | 4 | 4 | 5 | 5 | 5 | 5 |
400 | 4 | 5 | 5 | 5 | 5 | 5 |
450 | 5 | 5 | 5 | 5 | 5 | 6 |
500 | 5 | 5 | 5 | 5 | 6 | 6 |
600 | 5 | 5 | 5 | 6 | 6 | 6 |
700 | 5 | 5 | 6 | 6 | 7 | 7 |
800 | 5 | 6 | 6 | 7 | 7 | 7 |
900 | 6 | 6 | 6 | 7 | 7 | n/a |
1,000 | 6 | 6 | 7 | 7 | n/a | n/a |
The traffic data (in terms of ADT, Percent Directional Distribution, and Percent Trucks) are obtained from the traffic analysis report provided by TPP.
Trucks per day per lane = ADT
× PDD
× PT
× LDF
Where:
- ADT = average daily traffic for the first year of design period
- PDD = percent directional distribution of traffic (assume 50% split, unless observation proves otherwise)
- PT = percent trucks
- LDF = lane distribution factor; use 1.0 for 4 lanes or less, 0.7 for 6 lanes, and 0.6 for 8 lanes or more. The lane number is for both directions.
Example:
- Design Life = 10 years, ADT = 13,500, PDD = 63%, PT = 3.0%, and 4 lanes roadway, LDF =1.0
- Trucks per Day per Lane = 13,500 × 0.63 × 0.03 ×1.0 = 255
- For 255 trucks per day per lane and 10-yr. design, the required TWT thickness is 5 in.