4.3 Concrete Delivery Time
The concrete delivery time needs to be carefully monitored.
This is the time from when water is first added to the dry ingredients
of the mix until the truck is ready to discharge the concrete on
the project. This is particularly critical in hot weather when the
concrete may start to set prior to delivery. It should be regularly
monitored using the time stamp on the batch ticket from the plant.