4.4 Emulsion and Foamed Asphalt Treatments
Item 314 and various one-time use special specifications allow
the use of these additives. These treatment procedures are all intended
for reclamation of in-place pavement structures. Application is
typically accomplished using a reclaimer/recycler coupled to one
or more bulk tankers that supply the liquid treatment agents. Recycling
machines have become increasingly sophisticated and more powerful
over the years; up to 12-in. of existing pavement depth can be processed
with much improved distribution and uniformity of water and bituminous
treatment agents. The emulsion content is typically below 4.0%,
with the residual typically around 2.5%. Small percentages of lime
or cement (typically ≤ 1.5%), when required by the mix design, are
usually spread on the surface of the existing roadway ahead of the
recycling machine. These additives are lifted and mixed together with
the reclaimed roadway materials and liquid agents in the on-board
mixing drum in a single pass. The lime or cement additives serve
the following functions (
, 2012):
- improves adhesion of the bitumen to the aggregate,
- improves dispersion of the bitumen in the mix,
- modifies the plasticity of the natural materials (reduces PI),
- increases the stiffness of the mix and rate of strength gain, and
- accelerates curing of the compacted mix.
Alternately, a lime or cement slurry can be injected into
the recycler mixing chamber through a separate spray bar attachment.
These processes result in a product that locks up finer particles
by encapsulating them in bitumen, causing them to adhere to larger
particles that are not coated. The result is a material that remains
more flexible than other chemically-treated materials, but significantly
reduces the moisture sensitivity. A limitation for using these treatment
methods is the lack of knowledge and experience for many in the
mixture design and placement operations of these materials. Designing
a foamed asphalt mixture requires a specialized laboratory foaming
unit. Contact CST’s Geotechnical, Soils and Aggregates Branch for
assistance.
A significant precaution for these types of treatment options
is dredging up high PI subgrade material and mixing it with the
reclaimed pavement materials. The high PI materials will not disperse properly
and cannot be adequately coated with bitumen; hence the material
will remain moisture susceptible and prone to permanent deformation
(rutting). This is more likely to occur with thin existing structures
and structures with highly variable sectional thickness/composition
along the project. Where this condition is anticipated and high
PI soils are likely, the design process should include a preliminary
recycling pass using lime, or install a lift of flexible base before
the recycling pass to include this better material into the mix
and to avoid dredging up the subgrade material. Curing emulsion
treated layers to achieve strength and stability in a timely manner
may be problematic where moisture loss is delayed by environmental
conditions, such as high humidity or unanticipated high in-place
moisture contents. On the other hand, curing foamed asphalt treated layers
can often be achieved in approximately 2 hours, and the roadway
can be reopened to traffic.