2.2 Removing
Removing a load zone may be requested if rehabilitation or
reconstruction has been performed, or the load-zoned road can carry
the traffic until the next scheduled rehabilitation without premature failure.
If the highway was upgraded by using an approved design process
that accounts for future projected traffic, then no further analysis
is necessary and recommendation for removal of restrictions shall
be made by Executive Order. However, if an upgrade was accomplished
by means of a maintenance effort (or 2R program), then the district
must perform a deflection survey of the upgraded highway using the
load
zone
setup on the falling weight deflectometer (FWD).Refer to the step-by-step instructions in “Table 13-1: Changing
Load Zones on Roads” for removing a load zone.