Pavement Maintenance

The table below lists levels of service for pavement maintenance.
Pavement Maintenance
Condition
Desirable Level
Acceptable Level
Tolerable Level
Longitudinal Rutting
Maintain as follows:
Maintain as follows:
Maintain as follows:
0 - 500 ADT
< ½ & 50% per WP
< 1" & 50% per WP
< 3" & 25% per WP
501 - 10,000 ADT
< ½ & 50% WP
< 1" & 50% WP
< 3" & 25% per WP
10,001 & up ADT
< ½ & 25% per WP
< 1" & 25% per WP
< 1" & 50% per WP
Alligator Cracking
for all ADTs
Maintain with no visible cracks
Maintain with visible cracks , £ 10% per WP
Maintain with visible cracks £ 50% per WP
.
Ride Quality
Maintain as follows:
Maintain as follows:
Maintain as follows:
0 - 500 ADT
> 2.5 SI
> 2.0 SI
> 1.5 SI
501 - 10,000 ADT
> 3.0 SI
> 2.5 SI
> 2.0 SI
10,001 & up ADT
> 3.5 SI
> 3.0 SI
> 2.5 SI
Abbreviations:
Wheel path (WP), serviceability index (SI), average daily traffic (ADT)