Section 9: Bridge Preventive Maintenance Program
Background
The Bridge Preventive Maintenance Program (BPM) was developed to supplement funding for bridge maintenance. It is meant to bridge the gap between routine maintenance funding and the Bridge Rehabilitation and Replacement Program and is not intended to be used for previously scheduled bridge maintenance projects. The BPM is 100 percent state funded from Strategy 144.
The following are examples of the types of work eligible for consideration:
- Joint Cleaning and Sealing
- Joint Repairs
- Steel Piling Repairs
- Bearing and/or Bearing Pad Replacement
- Bearing Supplements for T-Girders
- Cap Repairs for Spalling (Pan and T-Girder Bridges Deck Repairs
- Concrete Repairs for Corrosion Damage
- Concrete Deterioration Treatments for Pre-stressed Beams
- Asphalt Plug Joint
- Bridge Rail Retrofits and Transitions
- Adjust Steel Shoes
- Channel Protection
- Bridge Painting
Eligible Bridges
This program is to address bridge problems early to substantially
extend the life. The goal is to address those bridges that are structurally
deficient (condition rating of 4 or less for deck, superstructure
or substructure) that will not be programed for federal funding
in the next 10 years. Bridges that are programmed for bridge rehabilitation
or replacement are not eligible for this program, unless recommended
by the Bridge Division.
Contracting
BPM projects are let in CMCS under Segment 78 like a routine
maintenance contract using "BPS" as the project class. MNT transfers
BPM funds to the district's Strategy 144 budget after letting. MNT
approval is required prior to contract award for any project that
has a low bid greater than 20 percent of the estimate shown on the
approved projects list. Districts have signature authority for change
orders. Upon request by the district, change orders may be funded
with program under-runs if available and with MNT approval.