CGP - Notices of Intent/Notices of Termination
The procedures for filing Notices of Intent (NOI) and Notices
of Termination vary by District. Contact your District Environmental
Quality Coordinator (DEQC) for specifics.
When applicable, follow these general guidelines for determining
your level of CGP coverage.
- Projects impacting less than one acre do not require coverage under CGP, but do require appropriate Best Management Practices (BMP).
- Projects not exempted by the CGP that disturb one or more acres require a Storm Water Pollution Prevention Plan (SW3P) and a Construction Site Notice (CSN) to be posted on the site prior to beginning work.
- Projects not exempted by the CGP that disturb five or more acres require a Notice of Intent (NOI) to be submitted to TCEQ prior to the commencement of earth disturbing activities. A Notice of Termination (NOT) must be submitted to TCEQ after construction is complete and the site has been re-vegetated to 70 percent of the native background cover.