Notification and Coordination
When the contractor or TxDOT staff member encounters materials
that, upon visual observation or odor, seem likely to contain hazardous
materials, he/she must notify the project/Area Engineer immediately,
per Item 6.10, TxDOT Standard Specifications . The Engineer must
take the following notification and coordination steps to deal with
hazardous materials after discovery:
- Secure the suspected area for worker and public safety as needed. If possible, relocate the contractor on the project to avoid or minimize construction downtime.
- Notify the Environmental Affairs Division (ENV) and the District Construction Office.
- Determine applicable regulations; ENV can assist. If notification is required or additional regulatory assistance desired, the district construction office should notify the local office of the Texas Commission on Environmental Quality (TCEQ). ENV is available to facilitate communication and coordination with the TCEQ.
- Confirm or evaluate whether special provisions are needed. The Engineer may contact ENV for assistance in contracting for statewide environmental engineering consultant services.
- If possible or practical, identify and notify the responsible parties for preventive action and/or cost recovery.
When hazardous materials are discovered, TxDOT assumes responsibility
from the contractor for testing, removal or disposition. The standard
provisions of the contract address compensation to the contractor
for delays and work stoppages. In accordance with Item 4.4 of the
TxDOT Standard Specifications, the contractor should be given the
option to perform the testing, removal and/or disposition as "extra
work" by a change order(s). The Engineer may need to obtain proposals
and estimated costs for "extra work" from consultants and/or specialty
contractors to compare with the estimate from the contractor. If
the “extra work” is not an option, work should be suspended wholly or
in part through proper notice to the contractor. If possible, re-deploy
the contractor on the construction project to avoid or minimize
construction downtime.
Another option is to arrange for an emergency contract for
a specialty contractor. Some districts may have prearranged purchase
orders for specialty contractors and/or laboratories. An environmental
consultant may be necessary for testing or developing preventive
action plans. ENV can provide statewide environmental engineering,
testing, consulting, remediation and abatement contract services
as needed.
Coordinate between the Construction Division (CST), the Design
Division (DES), ENV, the prime construction contractor, specialty
subcontractor, environmental consultant, responsible parties, and other
agencies. At this time, consider "partnering" to reduce the possibility
of future claims.
Coordinate the implementation of preventive action with the
construction activities of the project. This may involve concurrent
activities by consultants, specialty contractors, and the prime construction
contractor/subcontractors.
If work is suspended, then the District Construction Office
and Engineer will issue a "notice of resumption of suspended work"
to the prime construction contractor when preventive action is completed.