Project Development Considerations
Geotechnical Soil Borings/Soil Core Hole Drilling
Considerations:
If hazardous material contamination is
suspected, then any required soil core hole drilling for pavement,
retaining walls, bridges and other structures can be combined with
required environmental sampling and analysis to minimize costs.Additional provisions or contingency language may be needed
in the scope of services or proposals for geotechnical soil boring/soil
core hole contracts on a project-specific basis if contaminated
soil and/or groundwater might be encountered. For example, special
considerations for health and safety monitoring, personal protective
equipment, proper handling and disposal of soil cuttings, alternative
drilling techniques to prevent migration and plugging may be required
for soil core hole drilling.
Right-of-Way Considerations:
Regardless
of the potential for encountering contamination during construction,
special considerations for hazardous material concerns during the
right-of-way negotiation and acquisition process may be necessary.
Regulatory agency and property owner coordination may still be required,
depending upon the regulatory status of a site. For example, plugging
of groundwater monitoring or exploration wells may be required by
applicable regulations. Other concerns can include asbestos, underground
storage tank removal, permit status notifications, and site closure.Land use restrictions or post-closure care requirements may
be recorded in the deeds of parcels to be acquired. Corrective action
cases may need to be re-opened for sites or facilities due to proposed land
use changes. The terminology and requirements for corrective action
cases differ from those of a risk-based assessment for a facility
according to the federal or state regulatory status. For example,
requirements for a permitted landfill will differ from those for
a petroleum storage tank facility. Additional information on asbestos-containing
materials, petroleum storage tanks, leaking petroleum storage tank
facilities and other permitted or regulated sites is provided in
Chapter 3, “Right of Way.”
Utility or Pipeline Agreement and Adjustment Considerations:
Abandoned
utilities or pipe-lines containing crude oil, polychlorinated biphenyls
(PCB) or asbestos-containing materials (ACM) may have to be removed
during construction. TxDOT utility installation notices, joint use and
standard utility agreements typically include general statements
about following applicable federal, state, and local regulations.
The responsibilities for handling or disposing of hazardous materials
must be determined. On a case-by-case basis, specific hazardous
material or spill reporting requirements should be considered in
the agreements. If unknown or unanticipated contamination is encountered
during utility maintenance, adjustments or installation, the utility company
should be required by the agreement to notify the district so that
possible involvement during any proposed construction can be determined.The potential for encountering contamination should be addressed
early in project development to prevent or minimize delays in completing
utility adjustments. Adjustments to utilities or pipelines that
involve hazardous materials may impact construction projects. A
district may decide that a particular project requires joint bids
with the municipalities to handle utility adjustments during construction.
Whether the utilities are adjusted prior to or during construction,
the extra time needed to arrange for special handling of contamination
may delay construction, or impact construction scheduling. For example,
installation or adjustment of telephone fiber optic cable within
contaminated soil may require special protection, such as trench
lining and/or soil disposal.
Hydraulic and Storm Sewer Design Considerations:
If
handled improperly, de-watering and storm sewer installation in
contaminated soil or groundwater are at the greatest risk of worker exposure
and further releases into the environment. If unanticipated contamination
is encountered and special provisions or arrangements have not been
made, then construction delays and/or contractor disputes or claims
are likely. Areas needing significant excavation, trenching, tunneling and/or
de-watering typically require more assessment and/or further investigation
to determine if contamination will be encountered during construction.
If de-watering of contaminated groundwater is necessary, then specialty
contractors, engineering controls, monitoring and testing, temporary
collection, filtration, approval from regulatory agencies and/or
discharge permits may be required.Design Changes and Re-Evaluations:
The
following steps should be performed for design changes and re-evaluations:- Review documentation for original and/or subsequent ISA(s). If an ISA has not already been performed, one is required for the portions of the project that have not already been constructed.
- Review documentation for any investigations performed after the original environmental documentation, such as investigations to confirm the presence of, determine the extent of or determine proper handling requirements for contamination.
- Determine if any changes, new information or circumstances require further assessment, research or investigation. Re-evaluate the original ISA to determine if assumptions based on preliminary design or right-of-way requirements are still valid.
- Perform follow-up site visits and update regulatory database list searches.
Plans, Specifications and Estimates (PS&E) Considerations
:
If site remediation cannot meet regulatory closure requirements
prior to construction or during the right-of-way acquisition process,
then monitoring of remediation systems and their access may need
to be integrated into the design of the proposed project. Coordination
with regulatory agencies and the property owner/responsible parties
may be necessary to ensure that the roadway construction does not
adversely affect remediation, site closure and/or post-closure care
of the site.The management and disposal of contaminated soil, groundwater
and waste must be conducted in accordance with applicable federal
and state requirements and in a manner that will not adversely affect
human health and/or the environment. If a hazardous material concern
cannot be avoided prior to construction, a preventive action plan,
such as a Soil and Groundwater Management Plan, will serve to reduce
the impact of contamination encountered during construction. A preventive action
plan may include, but is not limited to, the following:
- Construction phasing
- Health and safety plans or considerations
- Waste management reuse or disposal options
- Permitting requirements
- Monitoring
- Sampling and analysis plans
- Specifications for engineering controls
- Filtration systems
- Ventilation systems
Special specifications, provisions or contingencies can be
incorporated into the PS&E to reduce the potential for construction
delays, claims, forced accounts, or field change orders. Employed
by the local entity, TxDOT or the prime highway contractor, specialty
contractors, or subcontractors can be used to implement the preventive
action plan during construction. Incorporating special specifications,
provisions or considerations into the development of the PS&E
is further discussed in Chapter 4, “Design.”
Property Management or Maintenance Considerations:
If
a site cannot meet regulatory closure requirements prior to construction
or during the right-of-way acquisition process, then closure may need
to be obtained after project construction. Additionally, a site
may have post-closure requirements for maintaining vegetation, caps
or drainage after construction. Any post-closure responsibility
must be communicated to the district maintenance staff.