Section 3: Peak Hour Projection Calculations

Data
Existing AM Peak Hour Counts
Existing Approach ADT = 16,000
NBL
NBT
NBR
250
1,000
250
Calculations
Existing AM Peak Hour Volume = 250 + 1,000 + 250 = 1,500
AM K Factor = Existing AM Peak Hour Volume/Existing Approach ADT
= 1,500/16,000
= .094
Growth Factor = 1.5
Projected Approach ADT = 16,000 * 1.5 = 24,000
AM Peak Hour Projections
.094*250*24,000/1,500
.094*1,000*24,000/1,500
.094*250*24,000/1,500
=376
=1,504
=376
NBL
NBT
NBR