2.4.3 What is the Difference between PBPD and Value Engineering?
FHWA views PBPD as the next step in the evolution of project development and design decision-making. Practical Design, Context Sensitive Solutions, Value Engineering and other similar initiatives and strategies are considered key components of a successful PBPD program.
Value Engineering:
- Method to determine the most cost-effective way to achieve proposed improvements;
- Typically focuses on maximizing project improvements; and
- Performed by multidisciplinary team not involved in the project.
PBPD:
- Method to determine the most cost-effective way to achieve the project objectives;
- Focuses on maximizing roadway system improvements, system safety, and TxDOT’s strategic goals; and
- Performed by project team and project stakeholders.