7.4.1 Contractor Review

DES-FPP uploads the plans and proposals for access by contractors for TxDOT’s bid lettings. The plans/proposal are uploaded to Plans Online. Plans/Proposals are posted 21 days prior to the first day of letting.
Districts should be aware that it can take 1 – 2 weeks for DES-FPP to upload project plans/proposal depending on the number of projects in the month’s letting schedule. Submit the RTL plan set as early as possible.