5.5.1 Overview

The project estimate should be entered into TxC and updated with each submittal so that the necessary funding amounts can be identified and tracked. Estimates can be entered into TxC as early as the Initial (30%) PS&E milestone. It is recommended to enter the estimate into TxC no later than the Detailed (60%) PS&E milestone so that modifications to funding amounts can be made well in advance of the project let date. Designers should confirm with the appropriate District/Division personnel what the expectations are for when the estimate should be entered into TxC. Projects with multiple CSJs require a separate Engineer’s Estimate for each CSJ.
Refer to the for specific details on entering the Engineer’s Estimate into TxC.