5.5.3 Calculating Mobilization for State Projects with multiple CSJs
For State projects the mobilization amount may be entered as lump sum amount under the controlling CSJ. However, in most cases it is recommended that the percentage of mobilization be pro-rated based on the percentage of overall contract cost, as outlined in
. An exception to this recommendation is if there is a large number of associated CSJs that would make this calculation complex. For example, a seal coat may include multiple associated CSJs across a District, in which case mobilization can be entered as a lump sum under the controlling CSJ.
Project bid items that are bid with the contract should be included with the mobilization for the project.
Joint bid utility items should be included with the ROW CSJ
. This should be calculated in the ROW CSJ, similar to a different CCSJ. If funding is available in the RCSJ, pay for mobilization in that RCSJ.