6.3.16 Relocation Certification

A Relocation Certification is required for every project. If any ROW was acquired, certification of proper relocation assistance is necessary.
The District Engineer signs project certifications which will be part of the project File of Record. A copy of the signed certifications is submitted, with other supporting documents, to DES for RTL PS&E document review and processing.
For any certification that is not clear prior to letting, a
Triple-Zero – 000 – Special Provision
notification to the contractor must be included in the bid proposal identifying the items that are not clear (e.g., ROW parcels, relocations, etc.) and the anticipated date of clearance. A
Construction Management Plan (CMP)
must be developed and submitted prior to letting in accordance with the PS&E Review and Processing Schedule. Refer to the CMP SOP for additional guidance.
  • Resources to consult:
  • Coordination:
  •  District ROW and utility staff
  •  District survey staff
  •  ROW staff
  •  TPD Local Governments Support Section staff
  •  County appraisal district staff
  •  County clerk’s office staff
  • Available training:
  •  CON812 – Local Government Project Procedures Qualification
  •  DES110 – Right of Way Considerations
  •  LPG101 – Local Government Project Procedures Qualification for TxDOT
  •  LGP102 – Local Government Project Construction Administration
  •  ROW001 – ROW Project Delivery Overview
  •  ROW099 – Introduction to Right of Way
  •  ROW690 – ROW Cost Estimating
  •  TPD319 – TxDOTCONNECT Right of Way and Utilities Overview
  •  TPD323 – TxDOTCONNECT Creating Parcels
  •  TPD359 – Advance Funding Agreements
  •  TxC training materials - Managing Right of Way