4.7.2 Environmental Technical Studies
See
for discussion on the environmental process and technical studies that are needed in order to obtain environmental clearance. The ROW footprint should be firmly established to begin detailed environmental studies.
This is a critical step in the project development process. Changes to the ROW footprint after this point could result in environmental studies rework and could negatively impact the project’s schedule and budget.
|