Acceptance of Baseline Schedules

The Engineer’s review and acceptance of the project schedule is for conformance to the requirements of the contract documents only and does not relieve the contractor of any responsibility for meeting the interim milestone dates (if specified). Review and acceptance does not expressly or by implication warrant, acknowledge, or admit the reasonableness of the logic or durations of the project schedule.