General Procedures

Use the available on the Construction Division webpage (internal access only). All letters regarding a default must be submitted to CST prior to sending to the contractor. Submit draft letters to for review and approval.
  • the
    Intent to Default
    letter must be signed at minimum by the Area Engineer in coordination with District Administration.
  • Default
    letters must follow the district’s latest Delegation of Signature Authority and may not be delegated below the Deputy District Engineer or District Director.
  • all letters require certified mail return receipt. Use the following as a best practice to ensure communication is made with the contractor for receipt of the letter:
    • certified mail (send to the physical address for the Prime Contractor).
    • email (include a delivery and read receipt for record).
    • phone call (document date, time, person talked to and description of conversation for record).
Voluntary Default
If a Contractor gives
written notice of Voluntary Default on the contract, TxDOT may forego the 10-day notice (Intent to Default) to default and immediately provide the contractor and surety a written notice of default.