General
The following procedures are required when interacting with potential bidders, virtually eliminating any risk for answering project pre-bid questions.
- Accept all simple or complicated questions via email, phone or in person and post in the web-based application the same day for the benefit of all perspective bidders.
- Post all responses, including the verbal answers to simple questions, to the (examples can be found on the CST Support page):
- For simple, straightforward answers, post on the same day
- Most questions should have detailed responses within 48 hours
- Acknowledge complicated questions that may require study and collaboration prior to responding, and these questions should be followed up in a timely manner.
- Avoid responses stating nothing more than, “Bid as Shown,” “Bid per plans,” or “Bid as advertised.”
- Special effort should be made to expedite answers during the week of letting, including the weekend prior to letting.Staff should be monitoring the Q&A the weekend before letting and should provide timely answers.
- If a potential bidder raises a question regarding an error in the plans:
- Acknowledge that you will research the potential error
- DO NOT make statements to that bidder, or any other potential bidder, that a possible or probable change to the plans, specifications, or quantities should be forthcoming
- Perform due diligence to determine whether the possible error is valid, and if so, ensure the error is addressed with:
- An addendum, prior to letting (refer toCCAM Chapter 2, Section4, "Addenda," for requesting a form and its corresponding SOP later in this chapter)
- A Change Order after letting and award
- A Postponement of letting to a later date.
- Responses posted to the web-based application trump any responses given verbally should there be a conflict.
- Take notes when discussing a project with a Contractor during the pre-bid period, including during non-mandatory pre-bid conferences, a ride-along, or when otherwise showing or discussing a project. Ensure to post all notes or meeting minutes to the web-based application for all prospective bidders.
- Post additional documentation requested that was not included in the plans.Documents thatcan be sharedare:
- Preliminary plans
- Cross Sections (PDFor XSR)
- CPM schedule
- Geotechnical data/reports
- DGN files (may only be provided to the awarded bidder).
- As-Built Plans (As-built bridge plans may be posted for informational purpose only. The only exception to this would be in the case when the plans requested are for Critical/Safety Sensitive structure. Refer to the .
Documents thatcannot be sharedare:- Engineer's estimate for individual bid items
- Global stability calculations
- Retaining wall and bridge calculations
- Ensure all interested parties are treated fairly and equitably.
- Keep a record of all information provided to the prospective bidders with the project files (electronically or hard copy). Instructions for printing, entering questions, uploading documents or answers on the web-based application can be found: – TxDOT/Bidder Version. For questions regarding TxDOTCONNECT Pre-Bid Q&A, email: .