How this Manual is Organized
This manual is organized into
15
chapters, as outlined in the following:- Chapter 1 - “Introduction” Provides a general overview of the purpose and scope of the manual.
- Chapter 2 - “Pre-Award Activities” Provides guidance onFHWA oversight, Local Government, pre-award activities such as competitive bid requirements, Pre-Bid Q&A, addenda, Pre-Bid conference, andContractor Signature of Authority.
- Chapter 3 - “Post-Award Activities” Outlinespost letting project information, legislative notification requirements,begin work, partnering, preconstruction and safety meeting.
- Chapter 4 - “Project Records and Closeout” Summarizes the importance of accurate project records, Traffic Control Plan (TCP) and project closeout.
- Chapter 5 - “Control of the Work” Covers project authority, work documents, staking the project, inspections, prime contractor performance evaluations and project evaluation.
- Chapter 6 - “Control of Materials” Summarizes the control of materials covering material management, sampling and testing, and required forms.
- Chapter 7 - “Changes to the Contract” Covers changes to the contract, including processing of change orders,approval authority, force accounts and othercontract agreements,etc.
- Chapter 8 - “Disputes and Claims” Outlines contract disputes and department claim process.
- Chapter 9 - “Legal Relations and Responsibilities” Covers legal relations and responsibilities.
- Chapter 10 - “Prosecution and Progress” Outlines project schedules, subcontracting, contract time, workday charges and time suspension, project timeliness, default of contractand terminations.
- Chapter 11 - “Measurement and Payment”Outlines estimates and issues affecting payments, material on hand,outlines the importance of prompt pay.
- Chapter 12 - “Environment” Provides insight into environmental permits, issues and commitments including other requirements. These topics include hazardous material/waste handling, biological and water resources, cultural resource management, noise/barriers,air quality,project-specific locations, and handling surplus materials.
- Chapter 13 - “Health and Safety” Provides information on health and safety laws and contract requirements.
- Chapter 14 - “Small Business Program” Provides an overview of the Department's Business Opportunity Programs.
- Chapter 15 - “Contractor Workforce” Covers items such as labor laws and On-the-Job Training (OJT).
- Chapter 16 - “FHWA Oversight Requirements” Outlines requirements including final inspection of federal-aid projects.