Contract Claim Committee Meeting
The CCC Chairperson will select Committee members at the time the meeting is scheduled, including Division Directors and one or more DEs, with a preference, if possible, for those whose Districts do not have a current contractual relationship with the prime contractor involved in a contract claim.
The informal meeting conducted before the CCC allows both the District and the contractor to discuss the claim. The meeting will be conducted in a cordial, professional, and orderly manner. As dispute negotiation discussions have not resolved the claim, any comments or presentations are to be directed to the CCC. Additional concerns may be brought before the CCC by a contractor, but additional claim issues not submitted in the initial claim or any claim amendments may not be considered.
After the meeting, the CCC Chairperson will send the contractor written notice of the Committee’s proposed disposition of the claim. The contractor must advise the CCC Chairperson in writing within 20 days whether the disposition is acceptable.