Defective and Unauthorized Work
Department resources may be used for the correction of defective
work, removal and replacement of defective work, or removal of unauthorized
work if the contractor fails to perform the corrections in a timely
manner. Deduct the cost of work performed by the Department from
any money due to the contractor.
Approval may be provided to the contractor to work beyond
the lines and grades given or shown on the plans, as deemed appropriate.
Do not reimburse the contractor for extra work performed without
written authority.
It is strongly recommended that Department inspectors not
allow full completion or corrections of pay items to be postponed
until the end of the project, to be added to a punch list, so there
is no chance it will be overlooked.