Districts may extend project limits without a CO if all the following conditions are met.
- Transition or tie-in work is less than 1,500 feet
- The work has a value of less than $50,000
- No changes made to unit bid prices
- The scope of work remains the same
- The funding category remains the same
- No new control section jobs (CSJ) are required
- No additional environmental clearance is necessary