Extending Project Limits to the Contract

Districts may extend project limits without a CO if all the following conditions are met.
  • Transition or tie-in work is less than 1,500 feet
  • The work has a value of less than $50,000
  • No changes made to unit bid prices
  • The scope of work remains the same
  • The funding category remains the same
  • No new control section jobs (CSJ) are required
  • No additional environmental clearance is necessary
If all the above conditions are not met, then a CO must be submitted for DE approval, regardless of the amount. Be sure to maintain the integrity of the competitive bid process.