Section 1: Overview
The term local government (LG) includes municipalities,
counties, county and regional toll authorities, metropolitan planning
organizations (MPOs), regional mobility authorities (RMA) and some
private entities. FHWA refers to this program as local public agency
(LPA).
A LG is required to manage and monitor federal-aid projects
to ensure that prime contractor and their subcontractors comply
with DBE Program provisions.
Prior to letting a construction project a DBE goal will be
set by TxDOT. Prior to contract execution, the LG will ensure the
prime contractor’s DBE commitments meet the goal and if not, reviews
and evaluates the prime contractor’s good faith efforts.
During construction, the LG is responsible for managing and
monitoring the project to ensure DBE Program compliance. This includes
conducting CUF reviews and ensuring the prime contractor does not
terminate or substitute the DBE without its written approval. And
finally, in the post award phase, payments made to DBE subcontractors
should equal the DBE goal commitment.
TxDOT is responsible for ensuring such projects are completed
in conformance with the DBE requirements in 49 CFR, Part 26.