Section 5: Daily Monitoring
District staff should note on their daily work
reports work performed by DBEs. The following observations should
be noted in the daily work reports specific to their operations:
- The names of the DBEs working on the project.
- Does the DBE have a foreman supervising the work or is the prime contractor or another subcontractor supervising the DBE’s work?
- Note the name of the foreman and who he works for.
- Is the DBE using its own equipment or that of the prime contractor?
- Note the company name on the equipment being used by the DBE.
- Is the DBE performing the work it was subcontracted to do or is the prime contractor or another subcontractor performing the work?
- Note the general description of the work the DBE subcontractor is performing or note if the prime contractor or another subcontractor is performing work that the DBE should be performing.
- Are the DBE’s employees performing the DBE’s work?
- Note if the DBE and prime contractor or other subcontractors are sharing employees.
If the project site inspector has reason to believe the DBE
subcontractor is not performing a CUF, document the observations
and bring them to the attention of the DDC and DOC for further investigation
and action.