Required Monthly Reporting Audit by the DDC
Each month’s total payments to the prime contractor will be combined and an audit will be created by DMS. The district staff will need to complete the audit by the end of the month. The District will utilize the following steps for the monthly audits.
Step 1:
Log in to DMS. Step 2:
Locate desired contract and navigate to Contract Management
page.Step 3:
Click on the Compliance Audit List
tab. The screenshot below shows the March 2017 audit has not yet begun. Audits will be added automatically.
/assets/Chapter-14/Section-4/audit_list.jpg/_jcr_content/renditions/cq5dam.web.1280.1280.jpeg)
Step 4:
Click on View Audit
under the Actions column. Screenshot showing March 2017 audit has begun and awaiting response from prime.
/assets/Chapter-14/Section-4/audit_lst_view_audit.jpg)
Step 5
: Verify payment from TxDOT to prime contractor is accurate. Step 6:
If the audit is incomplete, send reminder to the prime contractor./assets/Chapter-14/Section-4/audit_summary_edit.jpg)
If a prime contractor fails to report payments to subcontractors:
- Contact the prime contractor with a reminder of its contractual obligation.
- DBE prime contractors must report subcontractor activity for all subcontractors to include DBEs and non-DBEs.
Step 7:
Verify the prime contractor reported payments to the subcontractors (or zero payment entries if no work is performed). Step 8:
Verify the DBEs confirmed payment data received from the prime contractor. Scenario 1:
Prime contractor has not entered payment details./assets/Chapter-14/Section-4/subcon_no_pay_details.jpg)
Scenario 2:
Prime contractor has entered payments and one subcontractor has confirmed payment. Confirmation of payment by three subcontractors are still pending./assets/Chapter-14/Section-4/subcon_confirm_pending.jpg)
Scenario 3:
One of the subcontractors has indicated a discrepancy./assets/Chapter-14/Section-4/subcon_discrepancy.jpg)
Scenario 4:
Subcontractors have confirmed payment including final payment as selected by subcontractor./assets/Chapter-14/Section-4/subcon_final_confirmed.jpg)
Step 9
: If audit is to be the final audit, the District will select the mark as Final Audit
option on the Compliance Audit: [Month] [Year]./assets/Chapter-14/Section-4/audit_final_yes.jpg)