District Responsibilities
Performing a monthly audit in DMS
- On theContract Audit: Audit Summary for Total Contractpage, view the total payments TxDOT paid to the prime contractor and the reported payments the prime contractor paid to the subcontractors.
- Verify the total payments paid to the prime contractor are accurate.
- Verify the prime contractor reported payments to the subcontractors (or zero payment entries if no work is performed).
- Verify the DBEs’ confirmed payment data received from the prime contractor.
- Follow-up with prime contractor on any discrepancies.
- Complete audit by the end of the month.
If prime contractor fails to perform monthly audit:
- Contact the prime contractor with a reminder of its contractual obligation.
- When required, escalate the issue. Escalated actions may include suspending work, withholding all or a portion of an estimate, withholding project acceptance, placing contractor in default for breach of contract, or other actions deemed appropriate.