District Responsibilities

Performing a monthly audit in DMS
  • On the
    Contract Audit: Audit Summary for Total Contract
    page, view the total payments TxDOT paid to the prime contractor and the reported payments the prime contractor paid to the subcontractors.
  • Verify the total payments paid to the prime contractor are accurate.
  • Verify the prime contractor reported payments to the subcontractors (or zero payment entries if no work is performed).
  • Verify the DBEs’ confirmed payment data received from the prime contractor.
  • Follow-up with prime contractor on any discrepancies.
  • Complete audit by the end of the month.
If prime contractor fails to perform monthly audit:
  • Contact the prime contractor with a reminder of its contractual obligation.
  • When required, escalate the issue. Escalated actions may include suspending work, withholding all or a portion of an estimate, withholding project acceptance, placing contractor in default for breach of contract, or other actions deemed appropriate.