Section 2: Use of Joint Checks to Guarantee Payment for Materials and Supplies
District Responsibilities
Step 1:
Review DBE Joint Check Approval
Form 2178 and supporting documentation: - DBE’s written request to the prime contractor for the use of a joint check agreement.
- Documentation of DBE subcontractor applying for credit with the material supplier.
- Material supplier’s response to DBE subcontractor denying credit.
Step 2:
Verify or ensure the following: - The prime contractor has not required the subcontractor to use a specific supplier or the prime contractor’s negotiated unit price.
- The DBE subcontractor is more than an extra participant in releasing the check to the material supplier.
- The DBE subcontractor (not the prime contractor) negotiates the quantities, price and delivery of materials.
- The prime contractor issuing the check acts solely as guarantor.
- The DBE subcontractor releases the check to the supplier.
- The arrangement is short-term with the purpose being the DBE subcontractor’s establishment or increase of a credit line with the material supplier.
- The DBE subcontractor is responsible for both furnishing and installing the material/work item.
- The DBE subcontractor and the prime contractor must keep records of paid invoices and canceled checks as TxDOT will regularly be requesting them to ensure compliance.
Step 3:
Complete Form 2178 approving
or denying joint check arrangement. Step 4:
Respond in writing to prime contractor,
with a copy to the DBE subcontractor, approving or denying joint
check arrangement. (See Appendix A, Section 3 for sample letters) Step 5:
Periodically monitor the use
of joint checks. Step 6:
Request a copy of cancelled checks
for the months the contractor issued a joint check to each DBE with
an approved DBE Joint Check Approval. Step 7:
Ensure allowable goal credit
begins the date the joint check request is approved.