Section 2: District Responsibilities
- Manage change orders, which includes changes in the value and/or end date of the contract.
- Enter changes in DMS.
- Verify the prime contractor obtained sufficient DBE participation to meet the contract goal on the final contract value or made good faith efforts to do so.
- If the prime contractor could not obtain additional DBE participation, verify the prime contractor submitted a waiver request and evaluate good faith efforts to meet the goal on the final contract value.
If change orders eliminated work designated in a DBE commitment,
verify the prime contractor followed the termination procedures.