Increases of Scope of Work
If TxDOT issues a change order which increases or adds new
work items, the prime contractor must ensure that it has obtained
sufficient DBE participation to meet the contract goal on the final contract
value or has made good faith efforts to do so.
If the prime contractor determines that additional DBE participation
cannot be obtained, the prime contractor shall request a waiver
of the participation after submitting documentation of good faith efforts
to meet the DBE goal.