Chapter 5: Bridge Project Development Reference Information
Section 1: Requests for Development of Bridge and Geotechnical Work
Design Detail Requests
Submit all structures to be let under a single project as one submittal to ensure uniformity of design and eliminate duplication of standards. Submittal requirements for typical bridge layouts, and bridge layouts involving a railroad, are listed below. See Section 1 of this Chapter for the typical bridge project submission schedule.
The transmittal e-mail from the District to the Bridge Division project manager must contain the following information:
- District (both letting District and designing District, if different)
- County
- CSJ
- Facility carried and feature crossed
- Ready-to-let date and proposed letting date
- Project type (new construction, rehabilitation, replacement, widening, etc.)
- Point-of-contact information
- Pertinent, completed e-form:
- For bridge details, complete Form 2252 “Information Sheet for Structural Design” and select “Bridge Project” at the top of the form.
- For traffic structures, complete Form 2252 “Information Sheet for Structural Design” and select “TRF Structures Project” at the top of the form.
- For bridge rail details, complete Form 2448 “Information Sheet for Bridge Railing Upgrades, Retrofits & Repairs.”
- For geotechnical details, complete Form 2627 “Information Sheet for Geotechnical Design.” The Geotech form includes requests for borings, retaining walls, slope failures, and foundations.
- Approved preliminary bridge layout
- Soil boring data (either on layout or separate sheet)
- Typical sections sheet
- Construction sequence sheet
- A map view of the project illustrating the relationship of the roadways if the project is an interchange, or an interchange exists within the vicinity
- Existing bridge as-builts if relevant
Work Type | Small Scale | Large Scale | Specialty/Other |
---|---|---|---|
Borings: Bridge | All bridge lengths – 4 months | ||
Borings: Retaining Wall | All bridge lengths – 4 months | ||
Foundation Design# | L < 400 ft.; 1 Month | L > 400 ft.; 2 Months | L > 400 ft. Single Column Bents, Designed for Lateral Loading, Etc.; 3 to 4 Months |
Slope Stability Analysis** | L < 150 ft.; 1-2 Months | L > 150 ft.; 2-4 Months | |
Retaining Wall Design* | H < 20 ft.; L < 350 ft. 4 months plus the Retaining Wall Design time. | H < 20 ft.; 350 ft. < L < 1000 ft. 4 months plus the Retaining Wall Design time. | Total Time for Retaining Wall Detail Sheets = Retaining Wall Borings (4 months) + Wall Design time (project specific). |
MSE Wall | 1 Month | 1.5 Months | 2 Months |
Concrete Block Wall | 1 Month | 1.5 Months | 2 Months |
Sheet Pile | 2 Months | 2 Months | 2 Months |
Soil Nail | 1.5 Months | 2 Months | 3 Months |
Tie-Back | 2 Months | 2.5 Months | 3 Months |
Drilled Shaft | 2 Months | 2.5 Months | 3 Months |