Plans
For projects with bridge plans, follow these preparation guidelines.
- Obtain preliminary bridge layout approval prior to any percent PS&E submittal. Include preliminary retaining wall layouts with this submittal when necessary. See Section 1 of this chapter for more information.
- Ensure information on the title sheet corresponds with information on Design and Construction Information System (DCIS)and TxDOTCONNECT.
- Include the most current standards. All standards used must be clearly listed on the index of sheets even if unavailable at the time of submission.
- All modified (MOD) and special (SPL) standards must be signed and sealed by the responsible engineer. Include a brief description of the modifications, typically shown in the Revisions area of the title block.
- Show all hydraulic documentation correctly in the final plans as required by the Hydraulic Design Manualand the PS&E Preparation Manual. Hydraulic comments based on the preliminary submissions must be addressed prior to submittingnext stage ofPS&E.
- For projects involving a highway-railroad grade separation, an executed railroad agreement is required prior to letting. On federal oversight projects, send a copy of the agreement to the Federal Highway Administration (FHWA). Further information concerning railroad agreements can be found in Chapter 4 of this manual.