Requests for Attachments

The following outlines the process for requesting utility attachments to structures:
  • Requests originate from the utility company with an application to the
    District Engineer
    .
  • For attachments to structures within active projects, the
    District Engineer reviews requests, and if approved, forwards
    requests for attachment along with recommendations to the Bridge Division project manager for review and concurrence. The submission must include adequate justification, including details and an estimate for an independent utility crossing
    .
  • If the attachment is allowed, the Bridge Division project manager prepares a suitable agreement and forward
    s
    it to the
    District
    for partial execution with the utility company. Modification of the structural details to accommodate the utility and cost is the utility engineer’s responsibility.
  • The Bridge Division project manager coordinates the submission with the
    District
    . In addition, use and occupancy agreement forms are required as cited in Title 43 TAC, Section 21.52 (relating to Forms–General) and Title 43 TAC, Section 21.54 (relating to Use and Occupancy Agreement Forms).