Statewide Prioritization and Programming
The following process is used on a yearly basis to prioritize and program HBP projects:
- Bridge Division reviews the list of programmed bridges using HBP funds and coordinates with District and the Financial Management Division to verifyprojects in plan development andprojectsthatare programmed within the 24-month letting schedule.
- Bridge Division develops a list of eligible bridges for the District to review and submit for consideration for HBP funds.
- Bridge Division prioritizes the newly submitted bridges and ranks them according to theiroverallstatus:
- PrioritizingBridges that are:
- PoorCondition
- Fair Condition and Less than 26’ wide(inside of rail-to-inside of rail)
- Fair Condition and Scour Critical
- Fair Condition and Short spansover water with ahistory of debris accumulation resulting in scour.
- Fair Condition and have either Steel or timber piles
- Consideration is given to bridges that are eligible for replacement or rehabilitation and can be included with other planned projects along the same route to take advantage of the traffic control and mobilization costs of the contractor.
- Bridges are selected in this order until funding is exhausted within the year(s) that have available funding.
- Bridges not selected for a requested fiscal year due to fundingconstraints, are added to the following year for consideration and prioritized until funds are exhausted.
- This process is repeated for each year of the five-year HBP program listing until funds for all fiscal programming years have been exhausted.
Bridge Division encourages bridge projects selected within the first four years be developed AVL
with a
ndate
within the first two years of the program. This allows projects to be moved into the current fiscal year and be let for construction should another project be delayed.Program Time | Month | Time Frame | Action Items |
---|---|---|---|
List Development | August | 1 month | BRG develops lists of all eligible HBP projects. |
Program Call | September | 1 month | District select s new candidates and updates current estimates and lettings. |
Project Selection | October | 1 month | BRG develops list of District candidates |
Selection Comments | November | 2 weeks | District comment s on selections |
Program Call Finalized | December - January | 1.5 months | BRG prepares final call list |
Final list sent to FIN | January | End of month | BRG sends final HBP list to FIN. |
TXDOTCONNECT Updates | February | 1 month | District submit s TXDOTCONNECT changes and creates new CSJs. |