Off-System Project Funding
Off-System Project Funding
The entire Off-System project funding is approved up to the most reasonable termination point for approach work, not to exceed 150-ft average approach roadway length (300-ft total approach length). Items not eligible for federal funding are excluded and must be funded by another funding source.
If the project limits exceed the allowable length of approach road, as described above, then the following equation (% RD/BRG) is used to determine the maximum allowable Category 6 funds for projects up 15 million dollars.
- {% Road/Bridge Equation}: {[(Bridge Costs) x 1.25] + (Mobilization + SW3P + Traffic Handling and Barricades + Removal of the Old Structure + Approach Rail + Bridge Approach Slabs)}.
- Costs are limited to no more than 25 % Road/Bridge, and not greater than 2 times the cost of the Bridge Items.
All Off-System Projects over 15 million dollars will be evaluated on a case-by-case basis to determine the amount of Category 6 funds available, as well as any additional funding that is required to cover the funding gap.