Courtyard Drive/RM 2222
Loop 360 Projects
This project consists of improvements to the intersection at RM 2222, including a new Diverging Diamond Interchange (DDI). This project also includes improvements to the intersection at Courtyard Drive by removing the signal on the mainlanes and replacing it with an underpass.
Documents
Schedule
The project was environmentally cleared in spring 2021. Utility relocation will occur prior to the beginning of construction. Roadway construction is anticipated to begin in 2026.
Occasional lane closures may be required for utility relocation. Service interruptions are not anticipated. However, if you experience any service interruptions, please contact:
- Google: 855-867-5861
- Texas Gas: 800-959-5325
- AT&T: 800-288-2020
Past public involvement and events
Courtyard Drive/RM 2222 Public Hearing | Oct. 6, 2020
- Public Hearing Meeting Summary
- Presentation Video
- Presentation Transcript
- Display Boards
- Exhibit
- Handouts