Diana Underpass Closure - Starting May 7


Contact: Jennifer Wright

Phone: (915) 790-4340

Date: March 29, 2018


Starting May 7 at 7 a.m., the Diana underpass on Northeast El Paso is scheduled to close for at least 10 weeks. During this time, construction crews will be widening the bridge at that location.

Drivers should follow detours and expect a temporary U-turn at Hondo Pass for better access.

The work is part of the TxDOT US 54 Widening and Illumination project, which began in November 2017 and is expected to be complete by March 2019. The $35 million dollar project stretches from Hondo Pass to Loop 375/Transmountain. 

Once complete, each side of US 54 in those limits will have an added lane, high mast illumination, and turnarounds at Hondo Pass Avenue, Diana Drive, and at Loop 375 Transmountain. To improve safety in the area, the project will also reverse the existing on/off ramps in order to allow for traffic to merge on the access roads instead of the mainlanes. Pedestrians and residents will also enjoy a 2-mile shared use path that will be constructed northbound from Hondo Pass to Transmountain.

###

The Texas Department of Transportation is responsible for maintaining 80,000 miles of road and for supporting aviation, rail, and public transportation across the state. Through collaboration and leadership, we deliver a safe, reliable, and integrated transportation system that enables the movement of people and goods.  Find out more at TxDOT.gov. "Like" us on Facebook and follow us on Twitter.

Media Center