Section of US 79 to be Resurfaced in Panola County


Contact: Marcus Sandifer

Phone: (903) 799-1306

Date: March 27, 2020


A section of US 79 in western Panola County will receive a new riding surface during the couple of years according to plans approved in March by the Texas Department of Transportation (TxDOT).

“We will be resurfacing a 12.3-mile section of the highway from Rusk County Line to State Highway 149 in Carthage,” said Ray Brady, area engineer for TxDOT in Marshall.  “A little more work will be conducted on a 4.4-mile section beginning at the Rusk County Line. The old pavement will be removed, the base materials strengthened and then the entire roadway will be repaved.”

A.L. Helmcamp, Inc. of Buffalo, TX was awarded the contract for the construction project with a bid of $13.3 million.

Work on the project should begin in May of this year and take about 20 months to complete, Brady said.

###

The Texas Department of Transportation is responsible for maintaining 80,000 miles of road and for supporting aviation, rail, and public transportation across the state. Through collaboration and leadership, we deliver a safe, reliable, and integrated transportation system that enables the movement of people and goods.  Find out more at TxDOT.gov. "Like" us on Facebook and follow us on Twitter.