Detail Letting Schedule for Guadalupe County (FY 2023)
Bid Tabulations Dashboard
This report will no longer be updated, please access links on the Contract Letting page. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Guadalupe County (FY 2023) |
CCSJ: 0025-04-051 |
|||
District: | SAN ANTONIO | Let Date: | Jul 2023 |
Highway: | UA 90 | Let Status: | Tentative |
Project ID: | STP()HES | CSJ: | 0025-04-051 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | 500 FT EAST OF WEBER RD | Fund Cat: | 8 |
Limits To: | 500 FT WEST OF CR 202 (AUX AIRPORT RD) | ESTIMATE: | $1,174,372 |
Length: | 1.2 | Actual | $0 |
Back... | Totals for 0025-04-051 | ||
---|---|---|---|
Length: | 1.2 | ||
Estimate: | $1,174,372 | ||
Actual: | |||
CCSJ: 0025-10-097 |
|||
District: | SAN ANTONIO | Let Date: | Apr 2023 |
Highway: | FM 78 | Let Status: | Tentative |
Project ID: | STP ()HES | CSJ: | 0025-10-097 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | FLEMING ST | Fund Cat: | 8 |
Limits To: | 200' EAST OF 8TH ST | ESTIMATE: | $1,392,031 |
Length: | 0.6 | Actual | $0 |
Back... | Totals for 0025-10-097 | ||
Length: | 0.6 | ||
Estimate: | $1,392,031 | ||
Actual: | |||
CCSJ: 0366-02-094 |
|||
District: | SAN ANTONIO | Let Date: | Feb 2023 |
Highway: | SH 123 | Let Status: | Tentative |
Project ID: | NH () | CSJ: | 0366-02-094 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | FM 20 | Fund Cat: | 1 |
Limits To: | FM 758 | ESTIMATE: | $8,297,557 |
Length: | 5.7 | Actual | $0 |
Back... | Totals for 0366-02-094 | ||
Length: | 5.7 | ||
Estimate: | $8,297,557 | ||
Actual: | |||
CCSJ: 0915-46-054 |
|||
District: | SAN ANTONIO | Let Date: | Jul 2023 |
Highway: | VA | Let Status: | Tentative |
Project ID: | STP ()MM | CSJ: | 0915-46-054 |
Description: | BICYCLE AND PEDESTRIAN IMPROVEMENTS | Handling Code: | LC |
Limits From: | IN CIBOLO FROM SHAETHER ROAD/RECREATION | Fund Cat: | 3 |
Limits To: | FM 1103, SCHLATHER PARK | ESTIMATE: | $1,443,964 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0915-46-054 | ||
Length: | 0 | ||
Estimate: | $1,443,964 | ||
Actual: | |||
CCSJ: 2021-02-018 |
|||
District: | SAN ANTONIO | Let Date: | Aug 2023 |
Highway: | FM 1044 | Let Status: | Tentative |
Project ID: | STP ( )FRS1 | CSJ: | 2021-02-018 |
Description: | RAILROAD CROSSING IMPROVEMENTS | Handling Code: | XX |
Limits From: | 0.1 MI N OF FM 78 | Fund Cat: | 8 |
Limits To: | FM 78 | ESTIMATE: | $450,000 |
Length: | 0.1 | Actual | $0 |
Back... | Totals for 2021-02-018 | ||
Length: | 0.1 | ||
Estimate: | $450,000 | ||
Actual: |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |