Detail Letting Schedule for San Augustine County (FY 2021)
Bid Tabulations Dashboard
This report will no longer be updated, please access links on the Contract Letting page. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
San Augustine County (FY 2021) |
CCSJ: 0064-04-040 |
|||
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | SH 21 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0064-04-040 |
Description: | Hazard Elimination & Safety | Handling Code: | |
Limits From: | FM 3483 | Fund Cat: | 8 |
Limits To: | 0.352 MILES EAST OF FM 1 | ESTIMATE: | $89,404 |
Length: | 6.6 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | SH 21 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0064-04-041 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | FM 3483 | Fund Cat: | 8 |
Limits To: | 0.352 MILES EAST OF FM 1 | ESTIMATE: | $71,030 |
Length: | 0.0 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | US 96 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0064-06-056 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | FM 83 | Fund Cat: | 8 |
Limits To: | 0.383 MILES SOUTH OF SL 149 | ESTIMATE: | $83,583 |
Length: | 7.7 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | SH 21 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0118-10-067 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | 0.256 MILES WEST OF FM 1196 | Fund Cat: | 8 |
Limits To: | US 96 | ESTIMATE: | $112,834 |
Length: | 10.6 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 353 | Let Status: | Tentative |
Project ID: | STP ()HES | CSJ: | 0118-12-020 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | SH 147 | Fund Cat: | 8 |
Limits To: | 2.629 MILES NORTH OF FM 2785 | ESTIMATE: | $76,369 |
Length: | 0.0 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 2457 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0213-13-015 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | 0.228 MILES WEST OF FM 3277 | Fund Cat: | 8 |
Limits To: | US 190 | ESTIMATE: | $52,655 |
Length: | 4.6 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | SH 103 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0336-06-030 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | 2.761 MILES WEST OF FM 226 | Fund Cat: | 8 |
Limits To: | 0.375 MILES EAST OF FM 95 | ESTIMATE: | $91,966 |
Length: | 8.5 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | SH 103 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0336-08-028 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | 0.798 MILES EAST OF US 96 | Fund Cat: | 8 |
Limits To: | SH 21 | ESTIMATE: | $127,878 |
Length: | 9.6 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 224 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0403-02-021 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | SH 156 | Fund Cat: | 8 |
Limits To: | SH 156 | ESTIMATE: | $82,893 |
Length: | 7.7 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 1277 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0597-02-024 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | US 96 | Fund Cat: | 8 |
Limits To: | SH 103 | ESTIMATE: | $203,880 |
Length: | 14.4 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 2923 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0597-04-004 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | 1.558 MILES WEST OF FM 1277 | Fund Cat: | 8 |
Limits To: | FM 1277 | ESTIMATE: | $23,408 |
Length: | 1.6 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 83 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0694-01-028 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | FM 1 | Fund Cat: | 8 |
Limits To: | 0.617 MILES EAST OF FM 1175 | ESTIMATE: | $121,081 |
Length: | 10.3 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 83 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0694-01-029 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | FM 1 | Fund Cat: | 8 |
Limits To: | FM 1175 | ESTIMATE: | $102,012 |
Length: | 9.6 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 95 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0706-03-027 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | US 59 | Fund Cat: | 8 |
Limits To: | SH 7 | ESTIMATE: | $180,602 |
Length: | 13.6 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 132 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0737-02-017 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | 7.179 MILES SOUTH OF SH 7 | Fund Cat: | 8 |
Limits To: | SH 7 | ESTIMATE: | $77,081 |
Length: | 2.7 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 417 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0810-02-020 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | SH 87 | Fund Cat: | 8 |
Limits To: | FM 139 | ESTIMATE: | $150,412 |
Length: | 11.3 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 326 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0893-03-016 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | US 69 | Fund Cat: | 8 |
Limits To: | 6.766 MILES SOUTH OF US 69 | ESTIMATE: | $91,324 |
Length: | 1.2 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 343 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0926-02-013 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | 2.899 MILES EAST OF FM 851 | Fund Cat: | 8 |
Limits To: | FM 225 | ESTIMATE: | $74,566 |
Length: | 6.9 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 350 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0928-01-014 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | US 190 | Fund Cat: | 8 |
Limits To: | 0.189 MILES SOUTH OF FM 3126 | ESTIMATE: | $55,262 |
Length: | 0.0 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 352 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0929-01-022 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | US 59 | Fund Cat: | 8 |
Limits To: | US 287 | ESTIMATE: | $85,501 |
Length: | 8.0 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 1280 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0931-02-021 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | SH 19 | Fund Cat: | 8 |
Limits To: | 0.052 MI W OF TRINITY COUNTY LINE | ESTIMATE: | $98,233 |
Length: | 7.3 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 1280 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0931-02-023 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | 0.494 MILES EAST OF SH 19 | Fund Cat: | 8 |
Limits To: | TRINITY COUNTY LINE | ESTIMATE: | $72,855 |
Length: | 6.8 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 227 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0937-01-026 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | 5.135 MILES WEST OF FM 2544 | Fund Cat: | 8 |
Limits To: | 0.585 MILES WEST OF FM 1272 | ESTIMATE: | $153,816 |
Length: | 11.5 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 1275 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 1407-01-030 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | 0.866 MILES SOUTH OF SL 224 | Fund Cat: | 8 |
Limits To: | 0.967 MILES SOUTH OF RAPSILVER LN | ESTIMATE: | $90,763 |
Length: | 6.6 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 1279 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 1409-02-014 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | 1.434 MILES EAS OF SH 147 | Fund Cat: | 8 |
Limits To: | SH 87 | ESTIMATE: | $77,918 |
Length: | 5.7 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 1592 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 1510-01-020 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | FM 1 | Fund Cat: | 8 |
Limits To: | SH 184 | ESTIMATE: | $117,103 |
Length: | 8.7 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 343 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 2300-01-021 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | FM 225 | Fund Cat: | 8 |
Limits To: | US 59 | ESTIMATE: | $189,443 |
Length: | 14.3 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 1316 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 2510-01-019 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | SH 146 | Fund Cat: | 8 |
Limits To: | 2.205 MILES EAST OF SH 146 | ESTIMATE: | $25,826 |
Length: | 2.2 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 2497 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 2589-01-025 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | SH 94 | Fund Cat: | 8 |
Limits To: | US 59 | ESTIMATE: | $115,476 |
Length: | 8.6 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 2610 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 2591-01-013 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | SH 146 | Fund Cat: | 8 |
Limits To: | 4.962 MILES SOUTH OF SH 146 | ESTIMATE: | $54,221 |
Length: | 5.0 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 83 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 2637-01-027 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | SH 147 | Fund Cat: | 8 |
Limits To: | FM 2866 | ESTIMATE: | $201,793 |
Length: | 15.2 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 2663 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 2663-01-009 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | 1.435_MILES EAST OF US 287 | Fund Cat: | 8 |
Limits To: | FM 2022 | ESTIMATE: | $41,808 |
Length: | 3.0 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 2694 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 2700-01-020 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | FM 417 | Fund Cat: | 8 |
Limits To: | 1.584 MILES EAST OF FM 3172 | ESTIMATE: | $185,622 |
Length: | 13.4 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 2782 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 2808-02-008 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | FM 225 | Fund Cat: | 8 |
Limits To: | US 59 | ESTIMATE: | $121,224 |
Length: | 9.0 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 2782 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 2808-02-010 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | FM 225 | Fund Cat: | 8 |
Limits To: | US 59 | ESTIMATE: | $96,168 |
Length: | 9.0 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 3126 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 3160-03-008 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | US 190 | Fund Cat: | 8 |
Limits To: | FM 2457 | ESTIMATE: | $38,731 |
Length: | 2.7 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 3278 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 3198-02-016 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | FM 222 | Fund Cat: | 8 |
Limits To: | 0.850 MILES WEST OF FM 1988 | ESTIMATE: | $40,297 |
Length: | 3.6 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 3152 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 3220-01-011 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | US 190 | Fund Cat: | 8 |
Limits To: | FM 350 | ESTIMATE: | $89,339 |
Length: | 6.6 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 1475 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 3264-01-011 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | FM 841 | Fund Cat: | 8 |
Limits To: | FM 326 | ESTIMATE: | $23,721 |
Length: | 1.6 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 1336 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 3418-01-013 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | 1.814 MILES WEST OF FM 324 | Fund Cat: | 8 |
Limits To: | FM 324 | ESTIMATE: | $21,786 |
Length: | 1.8 | Actual | $0 |
District: | LUFKIN | Let Date: | Sep 2019 |
Highway: | FM 3520 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 3584-01-003 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | FM 3382 | Fund Cat: | 8 |
Limits To: | 1.854 MILES EAST OF FM 3382 | ESTIMATE: | $27,268 |
Length: | 1.9 | Actual | $0 |
Back... | Totals for 0064-04-040 | ||
---|---|---|---|
Length: | 279.4 | ||
Estimate: | $3,837,152 | ||
Actual: | |||
CCSJ: 0064-04-042 |
|||
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | FM 1 | Let Status: | Tentative |
Project ID: | STP () | CSJ: | 0064-04-042 |
Description: | Resurface Roadway | Handling Code: | |
Limits From: | SH 21 | Fund Cat: | 1 |
Limits To: | SAN AUGUSTINE COUNTY LINE | ESTIMATE: | $132,607 |
Length: | 2.3 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | FM 1 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 0064-05-062 |
Description: | Resurface Roadway | Handling Code: | |
Limits From: | SH 103 | Fund Cat: | 1 |
Limits To: | SH 184 | ESTIMATE: | $173,503 |
Length: | 4.6 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | US 287 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 0109-03-038 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | BU 287 | Fund Cat: | 1 |
Limits To: | 2.193 MI N OF FM 2663 | ESTIMATE: | $285,824 |
Length: | 4.1 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | US 287 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 0109-04-032 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | 2.193 MI N OF FM 2663 | Fund Cat: | 1 |
Limits To: | SL 304 | ESTIMATE: | $444,576 |
Length: | 6.3 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | SH 19 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 0109-06-043 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | LOVELADY CITY LIMITS SOUTH | Fund Cat: | 1 |
Limits To: | TRINITY COUNTY LINE | ESTIMATE: | $249,327 |
Length: | 4.0 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | SH 19 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 0109-07-052 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | HOUSTON COUNTY LINE_SOUTH | Fund Cat: | 1 |
Limits To: | 0.128 MILES S FM 1617 | ESTIMATE: | $632,286 |
Length: | 10.2 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | SH 19 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 0109-08-048 |
Description: | Resurface Roadway | Handling Code: | |
Limits From: | 0.128 MILES S FM 1617 | Fund Cat: | 1 |
Limits To: | TRINITY RIVER BRIDGE | ESTIMATE: | $589,600 |
Length: | 5.3 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | SH 21 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 0118-02-035 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | FM 1733 | Fund Cat: | 1 |
Limits To: | FM 227 NORTH | ESTIMATE: | $324,666 |
Length: | 7.2 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | SH 21 | Let Status: | Tentative |
Project ID: | STP () | CSJ: | 0118-06-074 |
Description: | Resurface Roadway | Handling Code: | |
Limits From: | 3.4 Miles W of Mill Creek | Fund Cat: | 1 |
Limits To: | US 59 | ESTIMATE: | $253,692 |
Length: | 3.3 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | SH 21 | Let Status: | Tentative |
Project ID: | STP () | CSJ: | 0118-06-075 |
Description: | Resurface Roadway | Handling Code: | |
Limits From: | FM 225 | Fund Cat: | 1 |
Limits To: | 3.48 Miles West of Mill Creek | ESTIMATE: | $238,505 |
Length: | 5.1 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | FM 415 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 0123-08-014 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | SH 87 | Fund Cat: | 1 |
Limits To: | FM 138 | ESTIMATE: | $280,844 |
Length: | 7.8 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | US 59 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 0175-05-044 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | SH 87 | Fund Cat: | 1 |
Limits To: | RUSK COUNTY LINE | ESTIMATE: | $613,751 |
Length: | 5.2 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | US 59 | Let Status: | Tentative |
Project ID: | NH ( ) | CSJ: | 0176-05-191 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | BU 59 N | Fund Cat: | 1 |
Limits To: | US 190 | ESTIMATE: | $130,445 |
Length: | 2.0 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | US 59 | Let Status: | Tentative |
Project ID: | NH ( ) | CSJ: | 0177-01-111 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | US 190 | Fund Cat: | 1 |
Limits To: | 1.6 MILES S. US 190 | ESTIMATE: | $104,827 |
Length: | 1.6 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | US 190 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 0213-05-041 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | JUST WEST OF FM 1276 | Fund Cat: | 1 |
Limits To: | TYLER COUNTY LINE | ESTIMATE: | $665,905 |
Length: | 10.2 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | SH 94 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 0319-04-087 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | FM 706 | Fund Cat: | 1 |
Limits To: | SL 287 | ESTIMATE: | $478,755 |
Length: | 3.9 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | SH 103 | Let Status: | Tentative |
Project ID: | NH ( ) | CSJ: | 0336-05-065 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | PAUL STREET | Fund Cat: | 1 |
Limits To: | FM 326 | ESTIMATE: | $422,453 |
Length: | 3.4 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | SH 103 | Let Status: | Tentative |
Project ID: | NH ( ) | CSJ: | 0336-07-070 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | SH 147 NORTH | Fund Cat: | 1 |
Limits To: | FM 1751 | ESTIMATE: | $400,000 |
Length: | 5.9 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | SH 147 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 0390-02-049 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | FM 83 | Fund Cat: | 1 |
Limits To: | ANGELINA RIVER BRIDGE | ESTIMATE: | $211,335 |
Length: | 5.5 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | SH 150 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 0395-03-044 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | FM 222 N INTERSECTION | Fund Cat: | 1 |
Limits To: | US 59 | ESTIMATE: | $566,093 |
Length: | 9.4 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | SH 156 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 0403-01-046 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | US 190 | Fund Cat: | 1 |
Limits To: | SH 150 | ESTIMATE: | $525,470 |
Length: | 14.2 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | SH 7 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 0553-02-018 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | US 69 | Fund Cat: | 1 |
Limits To: | NACOGDOCHES COUNTY LINE | ESTIMATE: | $218,205 |
Length: | 3.4 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | SH 7 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 0553-03-036 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | FM 2782 | Fund Cat: | 1 |
Limits To: | BU 59-F | ESTIMATE: | $420,587 |
Length: | 7.7 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | FM 1277 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 0597-03-013 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | SH 103 | Fund Cat: | 1 |
Limits To: | SH 147 | ESTIMATE: | $226,207 |
Length: | 5.9 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | FM 699 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 0809-01-032 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | US 84 | Fund Cat: | 1 |
Limits To: | FM 1656 | ESTIMATE: | $294,847 |
Length: | 8.2 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | FM 699 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 0809-06-001 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | FM 1656 | Fund Cat: | 1 |
Limits To: | SPUR 699 | ESTIMATE: | $67,507 |
Length: | 1.8 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | FM 226 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 0893-01-037 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | SH 103 | Fund Cat: | 1 |
Limits To: | END OF STATE MAINTENANCE | ESTIMATE: | $199,690 |
Length: | 5.7 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | SH 7 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 0894-01-021 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | SH 103 | Fund Cat: | 1 |
Limits To: | US 69 | ESTIMATE: | $450,149 |
Length: | 6.6 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | FM 138 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 0926-06-016 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | US 59 | Fund Cat: | 1 |
Limits To: | 1.1 MI W OF FM 415 | ESTIMATE: | $206,483 |
Length: | 5.8 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | FM 705 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 1079-01-035 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | FM 83 | Fund Cat: | 1 |
Limits To: | COUCHATAMA CREEK | ESTIMATE: | $91,825 |
Length: | 2.5 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | FM 705 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 1079-02-018 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | COUCHATAMA CREEK | Fund Cat: | 1 |
Limits To: | END OF PAVEMENT | ESTIMATE: | $338,934 |
Length: | 9.5 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | FM 947 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 1195-01-030 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | US 59 IN TIMPSON | Fund Cat: | 1 |
Limits To: | US 59 IN TENAHA | ESTIMATE: | $351,208 |
Length: | 11.3 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | FM 2022 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 1875-02-025 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | FM 2423 | Fund Cat: | 1 |
Limits To: | FM 2663 | ESTIMATE: | $300,000 |
Length: | 8.0 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | FM 1988 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 1876-01-038 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | US 59 | Fund Cat: | 1 |
Limits To: | 0.44 MILES SOUTH OF FM 3278 | ESTIMATE: | $224,949 |
Length: | 5.9 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | FM 942 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 1877-02-017 |
Description: | Resurface Roadway | Handling Code: | |
Limits From: | US 59 | Fund Cat: | 1 |
Limits To: | FM 62 | ESTIMATE: | $276,637 |
Length: | 0.0 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | FM 357 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 2117-02-014 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | FM 2262 | Fund Cat: | 1 |
Limits To: | POLK COUNTY LINE | ESTIMATE: | $178,358 |
Length: | 5.1 | Actual | $0 |
District: | LUFKIN | Let Date: | Nov 2019 |
Highway: | FM 3152 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 3220-01-012 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | US 190 | Fund Cat: | 1 |
Limits To: | FM 350 | ESTIMATE: | $252,915 |
Length: | 6.6 | Actual | $0 |
Bid List Back... | Totals for 0064-04-042 | ||
Length: | 215.5 | ||
Estimate: | $11,822,965 | ||
Actual: | |||
CCSJ: 0336-07-071 |
|||
District: | LUFKIN | Let Date: | Jan 2020 |
Highway: | SH 103 | Let Status: | Tentative |
Project ID: | NH ( ) | CSJ: | 0336-07-071 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | ATTOYAC RIVER | Fund Cat: | 1 |
Limits To: | SH 147N | ESTIMATE: | $8,700,000 |
Length: | 8.3 | Actual | $0 |
Back... | Totals for 0336-07-071 | ||
Length: | 8.3 | ||
Estimate: | $8,700,000 | ||
Actual: | |||
CCSJ: 0390-05-006 |
|||
District: | LUFKIN | Let Date: | Jan 2020 |
Highway: | FM 2558 | Let Status: | Tentative |
Project ID: | BR ( ) | CSJ: | 0390-05-006 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: | |
Limits From: | FM 2558 AT LITTLE OWL CREEK | Fund Cat: | 6 |
Limits To: | . | ESTIMATE: | $907,600 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0390-05-006 | ||
Length: | 0 | ||
Estimate: | $907,600 | ||
Actual: | |||
CCSJ: 0809-03-040 |
|||
District: | LUFKIN | Let Date: | May 2020 |
Highway: | US 96 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 0809-03-040 |
Description: | Construct New Roadway Lanes | Handling Code: | |
Limits From: | FM 3451 | Fund Cat: | 11 |
Limits To: | SH 21 | ESTIMATE: | $6,000,000 |
Length: | 2.7 | Actual | $0 |
Back... | Totals for 0809-03-040 | ||
Length: | 2.7 | ||
Estimate: | $6,000,000 | ||
Actual: |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |