Detail Letting Schedule for Wilbarger County (FY 2020)

Last Update: Monday, October 19, 2020

Bid Tabulations Dashboard

Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months.

The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Wilbarger County (FY 2020)

CCSJ: 0043-06-095

District:WICHITA FALLSLet Date:Nov 2019
Highway:US 70Let Status:Actual
Project ID:NH 2020(222)CSJ:0043-06-095
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:FM 1763 EXITFund Cat:1
Limits To:US 287 (CR 109)ESTIMATE:$723,968
Length:2.3Actual$622,212
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:SL 145Let Status:Actual
Project ID:C 43-15-4CSJ:0043-15-004
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:CR 113NFund Cat:1
Limits To:US 70ESTIMATE:$33,021
Length:0.8Actual$28,855
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:SL 404Let Status:Actual
Project ID:C 43-18-4CSJ:0043-18-004
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:US 70Fund Cat:1
Limits To:LP 145ESTIMATE:$15,549
Length:0.5Actual$14,014
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:SL 404Let Status:Actual
Project ID:C 43-19-4CSJ:0043-19-004
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:LP 145Fund Cat:1
Limits To:US 287ESTIMATE:$22,179
Length:0.6Actual$19,761
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:US 82Let Status:Actual
Project ID:NH 2020(222)CSJ:0044-07-072
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:MUENSTER ECLFund Cat:1
Limits To:FM 2739ESTIMATE:$182,981
Length:2.2Actual$166,644
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:US 82Let Status:Actual
Project ID:NH 2020(222)CSJ:0044-08-070
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:FM 2739Fund Cat:1
Limits To:LINDSAY WCLESTIMATE:$480,344
Length:5.8Actual$438,436
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:US 283Let Status:Actual
Project ID:STP 2020(227)CSJ:0125-03-049
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:FM 209Fund Cat:1
Limits To:SHACKELFORD COUNTY LINEESTIMATE:$113,493
Length:3.4Actual$104,061
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:SH 25Let Status:Actual
Project ID:STP 2020(227)CSJ:0137-03-083
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:0.519 MI S OF BU 287HFund Cat:1
Limits To:ARCHER COUNTY LINEESTIMATE:$507,599
Length:14.8Actual$469,759
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:US 82Let Status:Actual
Project ID:NH 2020(222)CSJ:0156-05-060
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:1.69 MIW OF FM 368Fund Cat:1
Limits To:0.795 MI E OF FERGUSON RDESTIMATE:$516,881
Length:9.3Actual$472,289
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:US 82Let Status:Actual
Project ID:NH 2020(222)CSJ:0156-06-058
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:1.1 MI E OF US 183/82 OVERPASS EBFund Cat:1
Limits To:1.0 MI W OF US 183 N INTERSECTION EBESTIMATE:$302,165
Length:6.8Actual$275,915
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:FM 51Let Status:Actual
Project ID:STP 2020(227)CSJ:0312-01-081
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:FM 1306Fund Cat:1
Limits To:DENTON COUNTY LINEESTIMATE:$799,134
Length:16.7Actual$730,513
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:FM 1806Let Status:Actual
Project ID:C 423-5-11CSJ:0423-05-011
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:END STATE MAINTENANCEFund Cat:1
Limits To:US 81ESTIMATE:$94,602
Length:2.9Actual$88,175
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:FM 1806Let Status:Actual
Project ID:STP 2020(227)CSJ:0423-06-014
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:US 81Fund Cat:1
Limits To:SH 59ESTIMATE:$293,252
Length:11.4Actual$266,617
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:FM 2179Let Status:Actual
Project ID:STP 2020(227)CSJ:0529-02-015
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:US 380Fund Cat:1
Limits To:CLIFF DR.ESTIMATE:$47,665
Length:0.0Actual$43,176
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:FM 91Let Status:Actual
Project ID:STP 2020(227)CSJ:0702-01-015
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:HARDEMAN COUNTY LINEFund Cat:1
Limits To:US 283ESTIMATE:$331,383
Length:0.0Actual$298,869
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:FM 369Let Status:Actual
Project ID:STP 2020(227)CSJ:0802-01-031
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:US 287Fund Cat:1
Limits To:BU 287JESTIMATE:$50,181
Length:1.0Actual$45,630
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:FM 369Let Status:Actual
Project ID:STP 2020(227)CSJ:0802-02-071
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:BU 287JFund Cat:1
Limits To:WICHITA RIVERESTIMATE:$156,133
Length:0.0Actual$142,973
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:FM 368Let Status:Actual
Project ID:STP 2020(227)CSJ:0804-04-028
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:BU 287HFund Cat:1
Limits To:FM 367ESTIMATE:$63,657
Length:1.9Actual$59,800
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:FM 1813Let Status:Actual
Project ID:C 804-5-8CSJ:0804-05-008
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:FM 368Fund Cat:1
Limits To:SH 240ESTIMATE:$46,244
Length:0.0Actual$41,829
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:FM 1153Let Status:Actual
Project ID:C 814-3-21CSJ:0814-03-021
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:END STATE MAINTENANCEFund Cat:1
Limits To:RM 1919ESTIMATE:$48,708
Length:0.0Actual$43,392
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:FM 3002Let Status:Actual
Project ID:STP 2020(227)CSJ:0815-09-008
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:IH 35Fund Cat:1
Limits To:FM 372ESTIMATE:$406,279
Length:0.0Actual$372,976
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:FM 433Let Status:Actual
Project ID:STP 2020(227)CSJ:0821-02-016
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:FM 2897Fund Cat:1
Limits To:US 70 NB EXIT RAMPESTIMATE:$20,298
Length:0.6Actual$18,199
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:VALet Status:Actual
Project ID:STP 2020(462)CSJ:0903-00-097
Description:PREVENTIVE MAINTENANCEHandling
Code:
 
Limits From:VARIOUS LOCATIONS DISTRICTWIDEFund Cat:1
Limits To:.ESTIMATE:$628,672
Length:1.0Actual$620,994
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:FM 578Let Status:Actual
Project ID:C 1031-6-9CSJ:1031-06-009
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:SH 79Fund Cat:1
Limits To:US 380ESTIMATE:$177,050
Length:7.0Actual$159,161
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:FM 1206Let Status:Actual
Project ID:C 1353-1-12CSJ:1353-01-012
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:SH 258Fund Cat:1
Limits To:FM 368ESTIMATE:$189,070
Length:8.0Actual$172,555
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:FM 1711Let Status:Actual
Project ID:C 1613-1-13CSJ:1613-01-013
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:BEGIN STATE MAINTENANCEFund Cat:1
Limits To:SH 79ESTIMATE:$89,360
Length:3.5Actual$80,455
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:FM 1769Let Status:Actual
Project ID:C 1711-1-30CSJ:1711-01-030
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:SH 16Fund Cat:1
Limits To:SH 114ESTIMATE:$374,297
Length:14.4Actual$340,358
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:FM 2071Let Status:Actual
Project ID:STP 2020(227)CSJ:1855-01-027
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:FM 372Fund Cat:1
Limits To:FM 922ESTIMATE:$247,111
Length:8.6Actual$230,227
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:FM 2072Let Status:Actual
Project ID:C 1856-2-9CSJ:1856-02-009
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:US 283Fund Cat:1
Limits To:END STATE MAINTENANCEESTIMATE:$112,734
Length:4.4Actual$101,940
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:FM 210Let Status:Actual
Project ID:STP 2020(227)CSJ:1956-01-011
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:SH 114Fund Cat:1
Limits To:YOUNG COUNTY LINEESTIMATE:$86,846
Length:0.0Actual$78,700
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:FM 2345Let Status:Actual
Project ID:C 2406-1-8CSJ:2406-01-008
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:FM 1739Fund Cat:1
Limits To:FM 368ESTIMATE:$138,672
Length:7.1Actual$128,492
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:FM 2459Let Status:Actual
Project ID:C 2460-1-9CSJ:2460-01-009
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:BEGINNING STATE MAINTENANCEFund Cat:1
Limits To:SH 79ESTIMATE:$74,018
Length:4.7Actual$67,683
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:FM 2847Let Status:Actual
Project ID:STP 2020(227)CSJ:2862-01-011
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:END STATE MAINTENANCEFund Cat:1
Limits To:SH 148ESTIMATE:$128,076
Length:4.9Actual$115,173
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:FM 3003Let Status:Actual
Project ID:STP 2020(227)CSJ:3018-01-010
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:WHITE ROSE RDFund Cat:1
Limits To:FM 61ESTIMATE:$148,295
Length:5.0Actual$139,836
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:FM 3327Let Status:Actual
Project ID:C 3517-1-8CSJ:3517-01-008
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:US 183Fund Cat:1
Limits To:END OF STATE MAINTENANCEESTIMATE:$60,950
Length:2.3Actual$55,007
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:FM 2953Let Status:Actual
Project ID:C 3562-1-5CSJ:3562-01-005
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:FM 103Fund Cat:1
Limits To:FM 677ESTIMATE:$227,286
Length:6.8Actual$209,321
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:FM 373Let Status:Actual
Project ID:STP 2020(227)CSJ:3569-02-004
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:FM 677Fund Cat:1
Limits To:COOKE CLESTIMATE:$24,255
Length:0.0Actual$22,142
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:FM 373Let Status:Actual
Project ID:STP 2020(227)CSJ:3569-03-007
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:MONTAGUE CLFund Cat:1
Limits To:FM 2383ESTIMATE:$134,638
Length:3.8Actual$123,916
 
District:WICHITA FALLSLet Date:Nov 2019
Highway:FM 440Let Status:Actual
Project ID:STP 2020(227)CSJ:3599-01-006
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:BU 82FFund Cat:1
Limits To:FM 1954ESTIMATE:$108,183
Length:0.0Actual$100,124
 
Proposal Request
List Showing Order
Bid List
Bid Tabulations
Award Status
Back...
Totals for 0043-06-095
Length:162.5
Estimate:$8,205,227
Actual:$7,510,177

CCSJ: 0147-01-022

District:WICHITA FALLSLet Date:Jan 2020
Highway:US 70Let Status:Actual
Project ID:STP 2020(453)CSJ:0147-01-022
Description:RESURFACE ROADWAYHandling
Code:
 
Limits From:US 287Fund Cat:11
Limits To:RED RIVERESTIMATE:$3,243,824
Length:5.9Actual$3,558,575
 
Proposal Request
Bid List
List Showing Order
Bid Tabulations
Award Status
Back...
Totals for 0147-01-022
Length:5.9
Estimate:$3,243,824
Actual:$3,558,575

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract