Detail Letting Schedule for Lamar County (FY 2020)
Bid Tabulations Dashboard
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Lamar County (FY 2020) |
CCSJ: 0045-09-104 |
|||
District: | PARIS | Let Date: | May 2020 |
Highway: | US 82 | Let Status: | Actual |
Project ID: | STP 2020(829)HES | CSJ: | 0045-09-104 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | US 271 | Fund Cat: | 8 |
Limits To: | FM 1508 | ESTIMATE: | $338,300 |
Length: | 6.0 | Actual | $366,585 |
District: | PARIS | Let Date: | May 2020 |
Highway: | BU 82-J | Let Status: | Actual |
Project ID: | STP 2020(829)HES | CSJ: | 0045-12-088 |
Description: | INSTALL ILLUMINATION | Handling Code: | |
Limits From: | AT N MARTIN LUTHER KING DR | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $22,796 |
Length: | 0.2 | Actual | $12,945 |
District: | PARIS | Let Date: | May 2020 |
Highway: | SH 11 | Let Status: | Actual |
Project ID: | STP 2020(829)HES | CSJ: | 0083-12-003 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | SH 11 | Fund Cat: | 8 |
Limits To: | FM 2297 | ESTIMATE: | $115,300 |
Length: | 1.7 | Actual | $93,696 |
District: | PARIS | Let Date: | May 2020 |
Highway: | SH 11 | Let Status: | Actual |
Project ID: | STP 2020(829)HES | CSJ: | 0108-09-051 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | BU 67 V | Fund Cat: | 8 |
Limits To: | SH 11 | ESTIMATE: | $57,900 |
Length: | 1.5 | Actual | $46,848 |
District: | PARIS | Let Date: | May 2020 |
Highway: | SH 37 | Let Status: | Actual |
Project ID: | STP 2020(829)HES | CSJ: | 0190-01-033 |
Description: | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | Handling Code: | |
Limits From: | YATES STREET | Fund Cat: | 8 |
Limits To: | TIGER FIELD ROAD (SCHOOL LN) | ESTIMATE: | $139,626 |
Length: | 0.7 | Actual | $146,895 |
District: | PARIS | Let Date: | May 2020 |
Highway: | SH 37 | Let Status: | Actual |
Project ID: | STP 2020(829)HES | CSJ: | 0190-01-034 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | YATES ST | Fund Cat: | 8 |
Limits To: | SCHOOL LN | ESTIMATE: | $282,272 |
Length: | 0.7 | Actual | $284,995 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0045-09-104 | ||
---|---|---|---|
Length: | 10.8 | ||
Estimate: | $956,195 | ||
Actual: | $951,964 | ||
CCSJ: 0045-09-105 |
|||
District: | PARIS | Let Date: | Jul 2020 |
Highway: | BU 82-H | Let Status: | Actual |
Project ID: | STP 2020(939)HES | CSJ: | 0045-09-105 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | 0.1 MI W OF FM 79 | Fund Cat: | 8 |
Limits To: | 0.1 MI E OF 33RD SE ST | ESTIMATE: | $870,350 |
Length: | 3.8 | Actual | $737,000 |
District: | PARIS | Let Date: | Jul 2020 |
Highway: | SH 78 | Let Status: | Actual |
Project ID: | STP 2020(939)HES | CSJ: | 0279-02-047 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | 0.1 MI N OF US 82 | Fund Cat: | 8 |
Limits To: | 0.1 MI S OF SH 56 | ESTIMATE: | $88,020 |
Length: | 2.1 | Actual | $65,170 |
District: | PARIS | Let Date: | Jul 2020 |
Highway: | SH 121 | Let Status: | Actual |
Project ID: | STP 2020(939)HES | CSJ: | 0549-01-039 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | 0.1 MI W OF W RUSSELL ST | Fund Cat: | 8 |
Limits To: | 0.1 MI E OF SH 56 | ESTIMATE: | $103,680 |
Length: | 1.8 | Actual | $81,680 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0045-09-105 | ||
Length: | 7.7 | ||
Estimate: | $1,062,050 | ||
Actual: | $883,850 | ||
CCSJ: 0045-15-012 |
|||
District: | PARIS | Let Date: | Dec 2019 |
Highway: | FM 1510 | Let Status: | Actual |
Project ID: | STP 2020(394) | CSJ: | 0045-15-012 |
Description: | PREVENTIVE MAINTENANCE | Handling Code: | |
Limits From: | FM 38 | Fund Cat: | 1 |
Limits To: | US 82 | ESTIMATE: | $373,305 |
Length: | 4.3 | Actual | $404,347 |
District: | PARIS | Let Date: | Dec 2019 |
Highway: | FM 64 | Let Status: | Actual |
Project ID: | STP 2020(394) | CSJ: | 0399-03-037 |
Description: | PREVENTIVE MAINTENANCE | Handling Code: | |
Limits From: | FM 1532 | Fund Cat: | 1 |
Limits To: | SH 24 | ESTIMATE: | $237,805 |
Length: | 6.6 | Actual | $211,681 |
District: | PARIS | Let Date: | Dec 2019 |
Highway: | FM 38 | Let Status: | Actual |
Project ID: | STP 2020(394) | CSJ: | 0435-01-076 |
Description: | PREVENTIVE MAINTENANCE | Handling Code: | |
Limits From: | FM 1509 | Fund Cat: | 1 |
Limits To: | FM 137 N | ESTIMATE: | $180,843 |
Length: | 5.0 | Actual | $160,996 |
District: | PARIS | Let Date: | Dec 2019 |
Highway: | FM 38 | Let Status: | Actual |
Project ID: | STP 2020(394) | CSJ: | 0435-01-077 |
Description: | PREVENTIVE MAINTENANCE | Handling Code: | |
Limits From: | FM 2352 | Fund Cat: | 1 |
Limits To: | US 82 | ESTIMATE: | $420,811 |
Length: | 10.6 | Actual | $374,695 |
District: | PARIS | Let Date: | Dec 2019 |
Highway: | FM 79 | Let Status: | Actual |
Project ID: | STP 2020(394) | CSJ: | 0688-02-062 |
Description: | PREVENTIVE MAINTENANCE | Handling Code: | |
Limits From: | FANNIN COUNTY LINE | Fund Cat: | 1 |
Limits To: | CR 34250 | ESTIMATE: | $432,834 |
Length: | 11.7 | Actual | $385,678 |
District: | PARIS | Let Date: | Dec 2019 |
Highway: | FM 195 | Let Status: | Actual |
Project ID: | STP 2020(394) | CSJ: | 0730-01-010 |
Description: | PREVENTIVE MAINTENANCE | Handling Code: | |
Limits From: | LAMAR COUNTY LINE | Fund Cat: | 1 |
Limits To: | FM 410 | ESTIMATE: | $84,187 |
Length: | 2.1 | Actual | $75,007 |
District: | PARIS | Let Date: | Dec 2019 |
Highway: | FM 195 | Let Status: | Actual |
Project ID: | STP 2020(394) | CSJ: | 0730-02-054 |
Description: | PREVENTIVE MAINTENANCE | Handling Code: | |
Limits From: | SS 139 | Fund Cat: | 1 |
Limits To: | AMHERST RD | ESTIMATE: | $42,484 |
Length: | 2.8 | Actual | $57,190 |
District: | PARIS | Let Date: | Dec 2019 |
Highway: | FM 195 | Let Status: | Actual |
Project ID: | STP 2020(394) | CSJ: | 0730-04-016 |
Description: | PREVENTIVE MAINTENANCE | Handling Code: | |
Limits From: | FM 410 | Fund Cat: | 1 |
Limits To: | FM 410 | ESTIMATE: | $507,508 |
Length: | 13.2 | Actual | $451,714 |
District: | PARIS | Let Date: | Dec 2019 |
Highway: | FM 38 | Let Status: | Actual |
Project ID: | STP 2020(394) | CSJ: | 0749-02-021 |
Description: | PREVENTIVE MAINTENANCE | Handling Code: | |
Limits From: | FM 137 N | Fund Cat: | 1 |
Limits To: | DELTA COUNTY LINE | ESTIMATE: | $202,558 |
Length: | 5.5 | Actual | $180,553 |
District: | PARIS | Let Date: | Dec 2019 |
Highway: | FM 195 | Let Status: | Actual |
Project ID: | STP 2020(394) | CSJ: | 1705-01-024 |
Description: | PREVENTIVE MAINTENANCE | Handling Code: | |
Limits From: | FM 410 | Fund Cat: | 1 |
Limits To: | SH 37 | ESTIMATE: | $98,906 |
Length: | 2.4 | Actual | $88,150 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0045-15-012 | ||
Length: | 64.2 | ||
Estimate: | $2,581,241 | ||
Actual: | $2,390,010 | ||
CCSJ: 0688-02-057 |
|||
District: | PARIS | Let Date: | Mar 2020 |
Highway: | FM 79 | Let Status: | Actual |
Project ID: | STP 2020(669) | CSJ: | 0688-02-057 |
Description: | PREVENTIVE MAINTENANCE | Handling Code: | |
Limits From: | SL 286 | Fund Cat: | 1 |
Limits To: | BU 82 H | ESTIMATE: | $871,914 |
Length: | 1.4 | Actual | $1,164,110 |
District: | PARIS | Let Date: | Mar 2020 |
Highway: | FM 1507 | Let Status: | Actual |
Project ID: | STP 2020(669) | CSJ: | 1452-01-015 |
Description: | PREVENTIVE MAINTENANCE | Handling Code: | |
Limits From: | SH 19 | Fund Cat: | 1 |
Limits To: | SL 286 | ESTIMATE: | $1,745,454 |
Length: | 2.9 | Actual | $1,886,227 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0688-02-057 | ||
Length: | 4.3 | ||
Estimate: | $2,617,368 | ||
Actual: | $3,050,337 | ||
CCSJ: 0769-02-033 |
|||
District: | PARIS | Let Date: | Jul 2020 |
Highway: | FM 906 | Let Status: | Actual |
Project ID: | STP 2020(940) | CSJ: | 0769-02-033 |
Description: | REHABILITATE EXISTING ROADWAY | Handling Code: | |
Limits From: | FM 2648 | Fund Cat: | 1 |
Limits To: | CR 47400 | ESTIMATE: | $2,772,581 |
Length: | 4.3 | Actual | $2,265,146 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0769-02-033 | ||
Length: | 4.3 | ||
Estimate: | $2,772,581 | ||
Actual: | $2,265,146 | ||
CCSJ: 0901-29-090 |
|||
District: | PARIS | Let Date: | Oct 2019 |
Highway: | VA | Let Status: | Actual |
Project ID: | STP 2019(787)TAPS | CSJ: | 0901-29-090 |
Description: | HIKE AND/OR BIKE | Handling Code: | |
Limits From: | 0.18MI N OF CARLA LEHAN AVE.RR CORR | Fund Cat: | 3 |
Limits To: | RRCR 2113 (LAMAR/RED RIVER CL) | ESTIMATE: | $1,300,232 |
Length: | 12.3 | Actual | $1,331,650 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0901-29-090 | ||
Length: | 12.3 | ||
Estimate: | $1,300,232 | ||
Actual: | $1,331,650 |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |