Detail Letting Schedule for Cherokee County (FY 2019)

Last Update: Monday, December 16, 2019

Bid Tabulations Dashboard

Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months.

The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Cherokee County (FY 2019)

CCSJ: 0198-07-014

District:TYLERLet Date:Jul 2019
Highway:SH 204Let Status:Actual
Project ID:STP 1902(166)CSJ:0198-07-014
Description:HIGHWAY IMPROVEMENTHandling
Code:
 
Limits From:US 79 IN JACKSONVILLE, SEFund Cat:1
Limits To:SH 110ESTIMATE:$14,677,601
Length:10.7Actual$13,705,298
 
Proposal Request
List Showing Order
Bid List
Bid Tabulations
Award Status
Back...
Totals for 0198-07-014
Length:10.7
Estimate:$14,677,601
Actual:$13,705,298

CCSJ: 0198-07-015

District:TYLERLet Date:May 2019
Highway:SH 204Let Status:Actual
Project ID:STP 2019(882)HESGCSJ:0198-07-015
Description:HAZARD ELIMINATION & SAFETYHandling
Code:
 
Limits From:SL 456 IN JACKSONVILLE, SEFund Cat:8
Limits To:SH 110ESTIMATE:$117,058
Length:9.5Actual$77,673
 
District:TYLERLet Date:May 2019
Highway:SH 64Let Status:Actual
Project ID:STP 2019(882)HESGCSJ:0245-07-030
Description:HAZARD ELIMINATION & SAFETYHandling
Code:
 
Limits From:SH 135, EFund Cat:8
Limits To:RUSK C/LESTIMATE:$52,810
Length:4.4Actual$46,883
 
District:TYLERLet Date:May 2019
Highway:SH 64Let Status:Actual
Project ID:STP 2019(882)HESGCSJ:0245-08-052
Description:HAZARD ELIMINATION & SAFETYHandling
Code:
 
Limits From:SMITH C/L, EFund Cat:8
Limits To:SH 42ESTIMATE:$28,995
Length:2.1Actual$25,327
 
District:TYLERLet Date:May 2019
Highway:SH 135Let Status:Actual
Project ID:STP 2019(882)HESGCSJ:0378-06-020
Description:HAZARD ELIMINATION & SAFETYHandling
Code:
 
Limits From:1.609 MI N OF FM 2064, W&SFund Cat:8
Limits To:1.564 MI NW OF US 69, J'VILLE CLESTIMATE:$87,356
Length:14.5Actual$80,322
 
District:TYLERLet Date:May 2019
Highway:SH 204Let Status:Actual
Project ID:STP 2019(882)HESGCSJ:0450-01-014
Description:HAZARD ELIMINATION & SAFETYHandling
Code:
 
Limits From:SH 110, SEFund Cat:8
Limits To:0.75 MI E OF FM 235ESTIMATE:$32,914
Length:5.2Actual$30,258
 
District:TYLERLet Date:May 2019
Highway:FM 315Let Status:Actual
Project ID:STP 2019(882)HESGCSJ:0890-02-019
Description:HAZARD ELIMINATION & SAFETYHandling
Code:
 
Limits From:HENDERSON C/L, SFund Cat:8
Limits To:0.005 MI S OF FM 3309 IN PALESTINEESTIMATE:$259,443
Length:19.8Actual$230,892
 
District:TYLERLet Date:May 2019
Highway:FM 747Let Status:Actual
Project ID:STP 2019(882)HESGCSJ:2407-02-009
Description:HAZARD ELIMINATION & SAFETYHandling
Code:
 
Limits From:6.262 MI N OF US 79, SFund Cat:8
Limits To:US 79ESTIMATE:$80,123
Length:6.3Actual$70,959
 
Proposal Request
List Showing Order
Bid List
Addenda
Bid Tabulations
Award Status
Back...
Totals for 0198-07-015
Length:61.8
Estimate:$658,699
Actual:$562,314

CCSJ: 0199-01-084

District:TYLERLet Date:Aug 2019
Highway:US 69Let Status:Actual
Project ID:NH 1902(286)CSJ:0199-01-084
Description:CONSTRUCT PEDESTRIAN INFRASTRUCTUREHandling
Code:
 
Limits From:NACOGDOCHES ST (0.1 MI S OF US79),SFund Cat:10
Limits To:TENA(.1 MI S OF FM768)IN JACK'VILLEESTIMATE:$604,150
Length:0.9Actual$502,100
 
Proposal Request
List Showing Order
Bid List
Bid Tabulations
Award Status
Back...
Totals for 0199-01-084
Length:0.9
Estimate:$604,150
Actual:$502,100

CCSJ: 0206-04-042

District:TYLERLet Date:Apr 2019
Highway:US 79Let Status:Actual
Project ID:NH 2019(733)CSJ:0206-04-042
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:2.8 MI W OF SH110 (C-S BREAK), WFund Cat:1
Limits To:3.5 MI E OF SH204,MUD CRK RELIEF BRESTIMATE:
Length:1.2Actual$3,225,388
 
District:TYLERLet Date:Apr 2019
Highway:US 79Let Status:Actual
Project ID:NH 2019(733)CSJ:0206-05-032
Description:HAZARD ELIMINATION & SAFETYHandling
Code:
 
Limits From:.16 MI E OF SH110 IN NEW SMMRFLD,EFund Cat:1
Limits To:2.8 MI W OF SH110 (C-S BREAK)ESTIMATE:$4,455,435
Length:0.0Actual$4,937,821
 
Proposal Request
List Showing Order
Bid List
Addenda
Bid Tabulations
Award Status
Back...
Totals for 0206-04-042
Length:1.2
Estimate:$4,455,435
Actual:$8,163,209

CCSJ: 0345-03-023

District:TYLERLet Date:Jan 2019
Highway:SH 110Let Status:Actual
Project ID:STP 2019(309)HESCSJ:0345-03-023
Description:INSTALL PROFILE EDGELINE & CENTERLINE MARKINGSHandling
Code:
 
Limits From:0.1 MI S OF FM1089-SMITH C/L, SFund Cat:8
Limits To:US 79 IN NEW SUMMERFIELDESTIMATE:$316,515
Length:10.9Actual$155,141
 
District:TYLERLet Date:Jan 2019
Highway:FM 347Let Status:Actual
Project ID:STP 2019(309)HESCSJ:0191-05-007
Description:INSTALL PROFILE EDGELINE MARKINGSHandling
Code:
 
Limits From:US 69 IN JACKSONVILLE, SFund Cat:8
Limits To:US 175ESTIMATE:$32,082
Length:2.4Actual$24,507
 
District:TYLERLet Date:Jan 2019
Highway:FM 347Let Status:Actual
Project ID:STP 2019(309)HESCSJ:0198-04-043
Description:INSTALL PROFILE EDGELINE MARKINGSHandling
Code:
 
Limits From:US 175 IN JACKSONVILLE, SFund Cat:8
Limits To:OLD US175/WOODROWESTIMATE:$6,284
Length:0.6Actual$3,219
 
District:TYLERLet Date:Jan 2019
Highway:US 79Let Status:Actual
Project ID:STP 2019(309)HESCSJ:0206-04-041
Description:INSTALL PROFILE EDGELINE & CENTERLINE MARKINGSHandling
Code:
 
Limits From:3.163 MI W OF SH 110-NEW SMMRFLD CLFund Cat:8
Limits To:1.108 MI E OF SH 204-J'VILLE CLESTIMATE:$44,177
Length:3.6Actual$27,555
 
District:TYLERLet Date:Jan 2019
Highway:SH 43Let Status:Actual
Project ID:STP 2019(309)HESCSJ:0207-02-029
Description:INSTALL PROFILE EDGELINE & CENTERLINE MARKINGSHandling
Code:
 
Limits From:4.5 MI S OF FM 2658, SFund Cat:8
Limits To:FM 1716ESTIMATE:$51,011
Length:5.6Actual$46,501
 
District:TYLERLet Date:Jan 2019
Highway:SH 43Let Status:Actual
Project ID:STP 2019(309)HESCSJ:0207-03-028
Description:INSTALL PROFILE EDGELINE & CENTERLINE MARKINGSHandling
Code:
 
Limits From:FM 2658, SWFund Cat:8
Limits To:4.5 MI S OF FM 2658ESTIMATE:$62,131
Length:4.6Actual$44,916
 
District:TYLERLet Date:Jan 2019
Highway:SH 110Let Status:Actual
Project ID:STP 2019(309)HESCSJ:0345-02-056
Description:INSTALL PROFILE EDGELINE & CENTERLINE MARKINGSHandling
Code:
 
Limits From:FM 1089 IN TROUP, SFund Cat:8
Limits To:0.1 MI S OF FM1089-CHEROKEE C/L, SESTIMATE:$3,422
Length:0.1Actual$1,178
 
District:TYLERLet Date:Jan 2019
Highway:FM 347Let Status:Actual
Project ID:STP 2019(309)HESCSJ:0378-07-032
Description:INSTALL PROFILE EDGELINE MARKINGSHandling
Code:
 
Limits From:OLD US175/WOODROW, SFund Cat:8
Limits To:US 84 AT OAKLANDESTIMATE:$142,776
Length:11.6Actual$104,899
 
District:TYLERLet Date:Jan 2019
Highway:SH 322Let Status:Actual
Project ID:STP 2019(309)HESCSJ:0594-02-028
Description:INSTALL PROFILE EDGELINE MARKINGSHandling
Code:
 
Limits From:GREGG C/L, SFund Cat:8
Limits To:FM 850ESTIMATE:$118,863
Length:9.9Actual$83,917
 
Proposal Request
Bid List
List Showing Order
Bid Tabulations
Award Status
Back...
Totals for 0345-03-023
Length:49.3
Estimate:$777,263
Actual:$491,834

CCSJ: 0926-01-023

District:TYLERLet Date:Jan 2019
Highway:FM 343Let Status:Actual
Project ID:STP 2019(429)HESCSJ:0926-01-023
Description:IMPROVE DRAINAGE AND CULVERTS FOR SAFETYHandling
Code:
 
Limits From:US 69Fund Cat:1
Limits To:2.76 MI E OF US 69ESTIMATE:$402,795
Length:2.8Actual$383,366
 
District:TYLERLet Date:Jan 2019
Highway:FM 1861Let Status:Actual
Project ID:STP 2019(429)HESCSJ:1673-03-009
Description:IMPROVE DRAINAGE AND CULVERTS FOR SAFETYHandling
Code:
 
Limits From:FM 316, EFund Cat:8
Limits To:VAN ZANDT COUNTY LINEESTIMATE:$339,102
Length:1.7Actual$255,232
 
Proposal Request
Bid List
List Showing Order
Bid Tabulations
Award Status
Back...
Totals for 0926-01-023
Length:4.5
Estimate:$741,897
Actual:$638,598

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract