The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Shackelford County (FY 2019)

CCSJ: 0125-04-033

District:ABILENELet Date:Jan 2019
Highway:US 283Let Status:Actual
Project ID:STP 2019(392)CSJ:0125-04-033
Description:REHABILITATE AND WIDEN ROADWAYHandling
Code:
 
Limits From:THROCKMORTON COUNTY LINEFund Cat:11
Limits To:US 180 IN ALBANYESTIMATE:$11,317,110
Length:17.3Actual$12,550,076
 
District:ABILENELet Date:Jan 2019
Highway:US 283Let Status:Actual
Project ID:STP 2019(430)HESCSJ:0125-04-029
Description:MILLED EDGELINE RUMBLE STRIPSHandling
Code:
 
Limits From:THROCKMORTON COUNTY LINEFund Cat:8
Limits To:2.717 MI S OF FM 2482ESTIMATE:$26,084
Length:15.1Actual$31,301
 
Proposal Request
Bid List
List Showing Order
Bid Tabulations
Award Status
Back...
Totals for 0125-04-033
Length:32.4
Estimate:$11,343,194
Actual:$12,581,377

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract