Detail Letting Schedule for Rusk County (FY 2018)

Last Update: Tuesday, February 06, 2018
Rusk County (FY 2018)

CCSJ: 0138-04-046

District:TYLERLet Date:May 2018
Highway:US 259Let Status:Approved
Project ID:C 138-4-46CSJ:0138-04-046
Description:REPAIR & REPAVE ROADWAY-NBL ONLYHandling
Code:
 
Limits From:US 79 IN HENDERSON, SFund Cat:1
Limits To:JARRELL CREEK, 2.8 MI N OF FM 1798ESTIMATE:$7,000,000
Length:7.6Actual$0
 
Back...
Totals for 0138-04-046
Length:7.6
Estimate:$7,000,000
Actual:

CCSJ: 0175-09-020

District:TYLERLet Date:Nov 2017
Highway:US 59Let Status:Actual
Project ID:NH 2018(252)CSJ:0175-09-020
Description:RESURFACE WITH SEAL COATHandling
Code:
 
Limits From:SHELBY COUNTY LINEFund Cat:1
Limits To:NACOGDOCHES COUNTY LINEESTIMATE:$117,197
Length:1.0Actual$160,759
 
Back...
Totals for 0175-09-020
Length:1
Estimate:$117,197
Actual:$160,759

CCSJ: 0393-02-027

District:TYLERLet Date:Jul 2018
Highway:SH 149Let Status:Tentative
Project ID:C 393-2-27CSJ:0393-02-027
Description:REPAIR AND RESURFACE ROADWAYHandling
Code:
 
Limits From:GREGG C/L, EFund Cat:1
Limits To:PANOLA C012303021ESTIMATE:$7,000,000
Length:6.5Actual$0
 
Back...
Totals for 0393-02-027
Length:6.5
Estimate:$7,000,000
Actual:

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract