Letting Schedule for Brownwood District (FY 2018)

Last Update: Tuesday, February 06, 2018
Brownwood District (FY 2018)
Brown | Comanche | Eastland | Mcculloch | San Saba | Stephens |

Brown County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
Description
0923-06-081VATentativeAug 2018$08INSTALL PROTECTIVE DEVICES
0128-01-112US 377TentativeAug 2018$08INSTALL PROTECTIVE DEVICES
0923-00-059VAApprovedMay 2018$1,500,0001THERMOPLASTIC STRIPING
2013-01-012FM 2125ApprovedApr 2018$1,248,9578SAFETY TREAT FIXED OBJECTS

Comanche County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
Description
0182-02-038SH 36ApprovedMar 2018$5,314,2981BASE OVERLAY,2 COURSE SURFACE TREATMENT, ACP
0923-17-077CRActualJan 2018$771,7156REPLACE BRIDGE AND APPROACHES
0183-01-043SH 36ActualOct 2017$1,309,5491ACP OVERLAY

Eastland County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
Description
0127-02-142US 183ApprovedMay 2018$10,450,0021RECONSTRUCT URBAN ROADWAY
0007-04-126SH 206ActualNov 2017$6,620,2721SEAL COAT
0127-01-031US 183ApprovedApr 2018$3,784,9701REHABILITATE EXISTING ROADWAY
0127-02-043US 183ApprovedApr 2018$5,209,1711ADD PASSING LANES
0127-02-141US 183ActualFeb 2018$4,279,8801ADD PASSING LANES

Mcculloch County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
Description
2561-01-011SH 71ApprovedMay 2018$2,578,8491REHAB EXISTING ROADWAY
0128-04-035US 190ActualJan 2018$8,490,4801RECONSTRUCT URBAN ROAD

San Saba County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
Description
0923-25-025VAApprovedApr 2018$120,55311LANDSCAPE DEVELOPMENT

Stephens County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
Description
0923-22-021CRActualOct 2017$819,9226REPLACE BRIDGE AND APPROACHES
0257-01-047US 183ActualNov 2017$307,47011DRAIANGE IMPROVEMENTS


Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract