Detail Letting Schedule for Hartley County (FY 2015)

Last Update: Tuesday, September 29, 2015
Hartley County (FY 2015)

CCSJ: 0041-01-045

District: Amarillo Let Date: NOV 2014
Highway: US 87 Let Status: Actual
Project ID: NH 2015(298) CSJ: 0041-01-045
Description: REHAB EXISTING ROADWAY Handling
Code:
 
Limits From: DALHART Fund Cat: 1
Limits To: HARTLEY Estimate: $6,101,079
Length: 12.0 Miles Actual: $6,272,206
 
District: Amarillo Let Date: NOV 2014
Highway: US 87 Let Status: Actual
Project ID: NH 2015(298) CSJ: 0041-01-046
Description: REHAB SBL OF EXISTING ROADWAY CONSISTING OF OV AND MBGF Handling
Code:
 
Limits From: DALHART Fund Cat: 1
Limits To: HARTLEY Estimate: $2,726,749
Length: 12.0 Miles Actual: $2,901,154
 
Back...

Totals for 0041-01-045
Length: 24.0 Miles
Estimate: $8,827,828
Actual: $9,173,360


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract