Detail Letting Schedule for Hale County (FY 2015)
Last Update: Tuesday, September 29, 2015
CCSJ: 0905-12-041
|
District: |
Lubbock |
Let Date: |
DEC 2014 |
Highway: |
VA |
Let Status: |
Actual |
Project ID: |
NH 2015(399) |
CSJ: |
0905-12-041 |
Description: |
REMOVAL & INSTALL OF LG GUIDE SIGNS |
Handling Code: |
|
Limits From: |
LUBBOCK COUNTY LINE |
Fund Cat: |
11 |
Limits To: |
SWISHER COUNTY LINE |
Estimate: |
$294,949 |
Length: |
37.7 Miles |
Actual: |
$246,777 |
|
Back...
|
Totals for 0905-12-041 |
Length: |
37.7 Miles |
Estimate: |
$294,949 |
Actual: |
$246,777 |
Handling Code |
Definition |
XX |
Project not processed through statewide letting |
TR |
Transfer of funds |
LC |
Project let through local entity |
NC |
Project not charged against district apportionment |
Let Status |
Definition |
Tentative |
Estimated letting date for this project |
Approved |
Project has administrative approval to be let |
Actual |
Project was let to contract |
|